Page 29 of 61
Budget Review 1 - Carryover Review 2016/17
Summary of Submissions Received $ 17,915,229.17 $ 12,948,685.09 $ 3,685,416.47 $ 4,966,544.08
Peay Joye e tire Cost Centre / Project Description 2015/16 Current 2015/16 Actuals Proposed Unspent Budget Capital / Council Contact Comments
Budget Carryover Avaiable for Operating
Amount Carryover
Cso08 Community Services Library Programs and Services $0.00 -($6,501.00) $6,501.00 $6,501.00 Operating Kerri Contini Allocation of State Library of Qld funding for Coding and Robotics digital literacy
program. Grant received 17/6/2016.
Cso0g Community Services Library Programs and Services $24,510.04 $16,050.00 $8,460.00 $8,460.04 Operating Kerri Contini In 2015/16 Dollars Making Sense Financial Literacy program had an
expenditure budget of $24,510. $16050 has been spent. Additional funding of
$12,000 due to be received during 2016/17.
CS010 Community Services Noosa Leisure Centre $53,889.00 $29,837.15 $6,650.00 $24,051.85 Operating Ash Saward Fencing works required to address a WHS issue which was identified late in the
financial year. The contractor was unable to complete the works prior to 30 June.
Cso12 Community Services Noosa Aquatic Centre $70,651.13 $44,497.24 $18,300.00 $26,153.89 Operating Ash Saward This carryover is proposed to fund the NAC plant and equipment condition
assessment and report, commencing 2 August 2016. The work was unable to be
completed prior to end of financial year due to availability of the contractor.
Cs013 Community Services Wild dog &fox trapping project $39,000.00 $0.00 $39,000.00 $39,000.00 Operating lan Florence Project trial of an intensive wild dog and fox trapping program over a period of 3
months using external contractors at an estimated cost of $39,000: Not
completed 15/16 due to delay in receiving contractors police arms use approval.
Exo001 Executive Office Local Economic Plan Implementation $70,000.00 $31,725.00 $24,000.00 $38,275.00 Operating Debra lezzi This proposal leverages work previously done by AEC for Council in the
provision of the economic profile. Council has committed to track key economic
indicators for the 5 year life of the current Local Economic Plan.
EX002 Executive Office Local Economic Plan Implementation $70,000.00 $31,725.00 $6,500.00 $38,275.00 Operating Debra lezzi Noosa Business Profile project - photography, business case studies and digital
document production and design.
EX003 Executive Office Sustainability Emissions Reduction Project $21,000.00 $13,842.00 $6,050.00 $7,158.00 Operating Debra lezzi Emission Reduction Project consultants - STAGE 1 of project was commenced
prior to end of 15/16, but not yet completed. The underspend of the current
budget for materials and services covers the required carryover.
P1001 Planning & Environmental Services $101,434.00 $48,414.00 $33,095.00 $53,020.00 Capital Peter Milne Development of Flying Fox Management Plan, Roost Management Permit, and
Infrastructure installation of Sprinkler systems at Wallace Park.
Page 29 of 61See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.