ORDINARY MEETING AGENDA 17 NOVEMBER 2022
Certification of piles condition
10. The installation of the piles must be supervised by a licensed cadastral surveyor.
Certification of the location of the installed piles prepared by a licensed cadastral
surveyor must be provided to Council.
The certification must:
a. state that the location of the piles is in accordance with the approved plans,
and
b. be submitted to Council prior to the installation/construction of any other
elements of the approved works
Currency
10.11. This approval lapses where the construction of the jetty extension and
pontoons have not commenced within 17 November 2028, unless application is
made and approved by Council for an extension.
Nature and extent of Use
11.12. All vessels, kayaks and SUPs for hire and all equipment associated with the
marine use of the facility must wholly moored/stored within the approved lease
area, with a maximum of 31 vessels at any one time.
12.13. All structures must be constructed wholly within the approved commercial
lease area as per the approved plans.
13.14. All commercial activities including, the loading and unloading of passengers
and boat docking is confined to the commercial lease areas of the respective
commercial operation.
Structures
14.15. All structures must use materials, natural finishes and colours that blend with
the surrounding natural landscape.
15.16. Structures must be designed and constructed such that they are free standing
within the waterway and are not connected to or behind the revetment wall or rock
wall.
16.17. Structures must be designed and constructed such that they do not place
additional vertical or lateral loads onto the existing revetment wall that may
compromise the long term stability and/or durability of the wall. Upon completion
of works, a certification by RPEQ must be provided to Council in this regard.
17.18. All structures must have no detrimental effects on stormwater drains and/or
easements.
18.19. No boatlifting devices are to be attached or moored at the structures for the
purpose of elevating a vessel above the water without Council approval.
19.20. The jetty and deck areas must be constructed in a manner to render the
underside area vermin proof.
20.21. There must be no electrical reticulation system carrying electricity in excess
of 24 volts beyond the revetment wall unless all switches and power outlets are
positioned above the 1% AEP flood level.
21.22. Lighting associated with the use must be designed, installed, operated, and
maintained in accordance with Section 3 of AS4282 Control of the Obtrusive
Effects of Outdoor Lighting.
22.23. Wastewater and sullage must only be disposed of at approved pump out
facilities.
Page 14 of 19
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.