2018-05-08 Services & Organisation Committee Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
ATTACHMENT 1
Page 51 of 107
OPERATIONAL PLAN 2017-18 PROGRESS REPORT ATTACHMENT 1
THE NOOSA ENVIRONMENT
No. Project Responsibility Update BS) ect)
1 Develop and commence implementation of Zero Emissions Environmental Services Manager The implementation of the action plan has commenced, in particular, the On track @
Action Plan following items:
- Governance structures in place and ongoing;
- Annual calculation of Council's footprint ongoing ;
- Ongoing regular internal communication ;
- Energy audits and development of the Marginal Abatement Cost Curve
(complete) ;
- Energy efficiency upgrades of lighting underway; and
- Procurement and Installation of Solar Systems at the NAC, The J, the
Depot and the Noosa Leisure Centre has commenced.
2 Implementation of Zero Waste Strategy: Roll out of 10,000 green waste bins has been completed with the Completed e
- Roll out of Garden Waste Recycling Bins Waste & Environmental Health Manager collection of these bins commencing in the first week of Sept. 2017.
- Introduce compostable dog waste bags Local Laws Coordinator Roll-out of new bags has been completed. Completed @
3 Ongoing negotiations with the Queensland Government Environmental Services Manager Initial negotiations have occurred with the Queensland Government and Behind Schedule Oo
regarding Noosa River management will continue to be progressed through the development of the Noosa
River Plan. The Draft Noosa River Plan is in the final stages of
development.
4 Pursue potential Yurol and Ringtail Forests environmental Chief Executive Officer Final contracts have been received and are currently being reviewed. On track @
project
5 Assist Noosa Biosphere Reserve with the UNESCO Biosphere Environmental Services Manager Staff are currently participating in a monthly meeting as part of the On track Qe
renewal process Biosphere Periodic Review Advisory Group to support and provide
information into the review and renewal process. The final document will
come to Council for consideration.
6 Finalise Environment Policy and Strategy and commence Director Environment & Sustainable Work is progressing with a scope being prepared for presentation to Behind Schedule @
implementation Development Council before June 2018. Significant background drafting and
consultation work has already been undertaken.
THE NOOSA COMMUNITY
No. Project Responsibility OF ote FC LT
1 Implementation of Social Strategy: Director Community Services Purchase of Johns Landing finalised 22 November 2017. Demolition of Completed @
- Purchase of Johns Landing and transition of long term buildings and final clean up finalised in March.
residents to alternative accommodation
- Finalise development of Arts and Cultural Heritage Plan and Director Community Services Draft plan scheduled for completion end of April 2018. On track Qo
commence implementation
- Finalise development of Sport and Recreation Plan and Director Community Services The final plan endorsed by Council in the October round of meetings. Completed @
commence implementation
2 Commence community consultation for an iconic playground at Infrastructure Planning, Design & Delivery A draft project management plan has been developed which includes On track @
Cooroy Manager stakeholder analysis, communications requirements, reporting and metric
collections.
3 Implementation of Library Strategic Plan Libraries and Galleries Manager Noosaville Library refurbishment and Radio Frequency Identification On track @
technology implementation underway.
4 Partner with the Cooroy Memorial Hall Committee for building Infrastructure Planning, Design & Delivery Asbestos removed from the building and restoration works completed. Completed @
restoration and refurbishment Manager Public opening on 21 April 2018.
5 Develop a Regional Art Gallery Strategy Libraries and Galleries Manager Development of the Regional Gallery strategy will commence in 4th Not started 2
Quarter 2018 following the appointment of the new Gallery Director and
the finalisation of the Cultural Plan.
Page 51 of 107See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.