2018-05-08 Services & Organisation Committee Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
Page 52 of 107
THE NOOSA ECONOMY
No. Project Responsibility Update Status
1 Commence renewal of Park Road boardwalk Infrastructure Planning, Design & Delivery The Principal contractor has been appointed, construction to commence On track @
Manager in the second half of April.
2 _ Finalise construction of Rufous Street Digital Hub project (Stage Economic Development Manager Construction of the Digital Hub building and restoration of the surrounding On track @
1) and adoption of hub operating model parkland completed. New Director of Digital Hub appointed. Tender for
tenanting of Digita Hub underway.
3 Continued implementation of Local Economic Plan _ incl. Economic Development Manager Continued to deliver on Local Economic Plan Priority actions, highlights On track @
providing support to existing industry representative groups and include:
evaluation of peak body models - The launch of the Economic Grants Program and guidance being
provided to a range of industry representative groups on potential
initiatives; and
- Strong industry engagement in relation to the development of the New
Planning Scheme.
LONG TERM PLANNING FOR NOOSA SHIRE
No. Project Responsibility Update SELL)
1 Finalise drafting of new Noosa Planning Scheme and obtain Planning Scheme Project Manager Drafting is nearing completion. Content now being extensively reviewed. On track @
Queensland Government approval Councillor workshops have continued through this quarter. The formal
notice from the Chief Executive of the Department of State Development,
Manufacturing, Infrastructure and Planning in response to Council's
resolution under the Planning Act was received late in the quarter.
2 Develop Climate Change Adaptation Plan & actions (Stage 1) Project Coordinator - Climate Change Coastal hazards adaptation plan project on schedule. Stakeholder On track @
Adaptation engagement has been initiated.
3 Finalise Noosa River foreshore management plan and Property Manager Draft Master Plan public consultation completed. To be reported to On track @
commence implementation Council shortly.
4 Complete detailed asset management plans for identified pilot Asset Planning Manager Noosa Aquatic Center Asset Managment Plan (AMP) adopted by Council On track @
areas and commence development of asset management plans in March & Slurry Systems AMP adopted by Council in April. Roads &
for the remaining infrastructure classes Bridges AMP's drafted for completion at the conclusion of the revaluation
period to factor in adjusted unit rates and depreciation. AMP's expected
to be presented to Council in June round of meetings.
5 Commence implementation of priority actions from Council's Director Infrastructure Services Consultants engaged to undertake investigations into the key priorities. On track @
Transport Strategy Working Groups and Steering Group have been established. A
Councillor Workshop to discuss ‘quick wins' undertaken on 19 April 2018.
6 Commence detailed design of North Shore Beachfront Property Manager Detailed design is in progress with construction due to commence in On track 7)
campground redevelopment including environmental restoration 2018/19.
works
7 Review of Noosa Community Support operating model in Community Facilities Manager Discussions with the Federal and State Funding agencies regarding the Completed @
preparation for new funding arrangements operations of Noosa Community Support undertaken and current
business model is to continue.
8 Development of a robust 10-year Capital Works Program Asset Planning Manager 5 year capital program drafted for budget consideration. 10 year capital Ontrack @
program to be complete by the end of June.
Page 52 of 107See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.