06/2361 - SUPERSEDED Negotiated Decision Notice [As Published] · 132006.2361

of 11

Text shows just the words. Original shows the document exactly as it was published.

NOOSA COUNCIL IDAS Development Application Decision Notice                                                 6 of 11


       To this end, a detailed maintenance plan shall be prepared for the proposed grease/oil arrestors, which
       shall be submitted to the Council for approval prior to obtaining a Development Permit for Operational
       Works.
       The approved maintenance plan shall be incorporated in the Community Management Scheme for the
       development and a copy of this shall be provided for Council’s records prior to commencement of the
       approved Use.
       A Development Permit for Building Works shall not be granted until a Development Permit for Operational
       Works has been issued in regard to the drainage scheme.
37.    All site stormwater drainage shall be by means of a gravity system.
Sewer Mains
38.    The site shall be connected to Council’s existing sewerage reticulation systems and be constructed in
       accordance with Council’s standards and requirements at no cost to Council.
Town Water Supply
39.    The site shall be connected to Council’s existing town water supply and be constructed in accordance with
       Council’s standards and requirements at no cost to Council.

40.    Each individual water connection to the water reticulation system shall extend to the property boundary
       and be metered. All fees for the supply of water meters shall be paid to the Council.

41.    All water meters must be located outside the property boundary and in an easily assessable location to
       facilitate unhindered reading by Council and/or Council’s contracted water meter readers, and not behind
       fences or locked gates. In this regard approval of the water meter configuration and location must be
       obtained from Council’s Water & Sewerage Capital Works Manager prior to lodgement and approval of
       hydraulic drawings.

42.    For Multiple Uses (including Building Format Plans, Group Title Plans, etc) the development shall be
       served by:

       42.1. A single Body Corporate water meter to measure the total water consumption (including fire hose
             reels, but excluding fire hydrants and fire sprinkler systems), and

       42.2. Individual water meters to each tenement capable of being separately rated, and

       42.3. A fire service (fully testable single detector check with metered bypass), where applicable, for flows
             to fire hydrants and fire sprinkler systems (excluding fire hose reels).
Service Easements (Sewer / Stormwater)
43.    To ensure Council’s sewer main and stormwater infrastructure is accessible for maintenance purposes
       and is protected from risk of damage no structures requiring a building permit (eg. buildings, swimming
       pools, retaining walls exceeding 1m in height, raised terraces, screens, etc) shall be constructed within or
       encroach over an easement.
Headworks Contributions
44.    Contributions shall be paid to Council in accordance with Planning Scheme Policies PSP17 and PSP16
       on Water Supply Headworks Contributions and Sewerage Headworks Contributions respectively and at
       the rates applicable at the time of payment. An estimate only of the contribution rates under the current
       policies is outlined below. These amounts will adjusted in line with changes to the Consumer Price Index,
       All Groups Brisbane from September 2006 until the date of payment.
       Water Supply         $1,803
       Sewerage             $1,213
       TOTAL                $3,016
       All headworks contributions must be paid prior to the issue of a Development Permit for Operational
       Works.
       Alternatively a trading bank guarantee shall be submitted to Council plus 20%. Should the headworks
       contributions not be paid at the due time, Council shall call upon the trading bank guarantee in full.
       In the event that the Development Permit for Material Change of Use of Premises lapses or is cancelled,
       the contribution or trading bank guarantee will be returned




A c:\docume~1\tblogg\locals~1\temp\bcl technologies\easypdf 5\@bcl@a4077865\@[email protected]

Used in these records

About this file

File size
60 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

06_2361 - SUPERSEDED Negotiated Decision Notice [As Published].pdf · 60 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.