NOOSA COUNCIL IDAS Development Application Decision Notice                                                    5 of 11


24.    A minimum of 2 covered carpark spaces and 1 uncovered carpark space shall be provided on site.

25.    The visitor carspace shall be located clear of the access driveway and have minimum dimensions of 5.4m
       x 2.4m clear of any walls or fencing.

26.    Vehicle access to the visitor carspace shall not be restricted by gates, security screens or any other
       obstacles.

27.    The carparking area shall be designed to comply with the provisions of AS/NZS 2890.1-2004 for user
       class 1A with allowance for vehicles to enter and leave the site in a forward gear and with a minimum
       head clearance (headroom) at any point of 2.2m.

28.    All carparking shall be kept, maintained and line-marked in a condition fit for use.

Public Open Space Contributions

29.    A Public Open Space contribution of $1,329 towards the acquisition of additional parkland or the
       improvement of existing parkland and facilities in the locality shall be paid to the Council prior to obtaining
       a Development Permit for Operational Works in accordance with Council’s Planning Scheme Policy
       PSP12 Public Open Space Contributions (Park). This amount will be subject to variations in the
       Consumer Price Index, All Groups Brisbane from September 2006 until the date of payment.
Frontage Works
30.    Footpath improvements such as topsoiling, grassing, and tree planting are required to the Grant Street
       frontage of the site in accordance with Planning Scheme Policy PSP03 Landscaping Plants & Guidelines.
       Grass shall be couch, free of weeds.

31.    A contribution of $1,010 towards the construction of footpaths in the Grant Street local area shall be paid
       to Council prior to obtaining a Development Permit for Operational Works. This amount will be subject to
       variations in the Consumer Price Index, All Groups Brisbane from September 2006 until the date of
       payment.

32.    All redundant vehicular crossings to the site shall be removed and replaced by kerb & channel, footpath
       paving and landscaping such as trees and grasses in accordance with Council’s Standard specifications
       prior to commencement of the use permitted by this permit.
Pathway Trunk Network Contributions
33.    A pathway trunk network contribution of $956 towards external major pathways, in accordance with
       Planning Scheme Policy PSP20 Pathway Trunk Network Contributions, shall be paid to the Council prior
       to obtaining a Development Permit for Operational Works. This amount will be subject to variations in the
       Consumer Price Index, All Groups Brisbane from September 2006 until the date of payment.
Stormwater Drainage
34.    All stormwater drainage shall be collected on site and discharged so there is no net increase in
       stormwater runoff from the site. Stormwater drainage permitted to drain from the site shall be discharged
       to Council’s existing drainage structures located at the rear of the site. Plans of the drainage design shall
       be prepared by a Registered Professional Civil Engineer and submitted to Council prior to obtaining a
       Development Permit for Operational Works.

35.    Roof runoff from any new dwelling shall be directed to a rainwater storage system or tank (minimum
       storage 3000 litres per dwelling/unit) that is installed to ensure water from the tank can be used for
       external uses (such as watering gardens, irrigation, ornamental ponds, water features, topping-up
       swimming pools, outdoor cleaning, etc) and for use in flushing of toilets internal to the dwelling. All
       rainwater tanks are to be designed and installed in accordance with the Queensland Development Code
       (QDC), Part 25 – Rainwater Tanks, and shall be part of the plumbing application in conjunction with the
       building approval. The location and capacity of the tanks shall be clearly shown on the plans submitted
       for Building Works approval and any overflow shall be directed to the stormwater drainage system.

36.    To ensure that polluted run-off does not enter Council’s stormwater drainage system, stormwater run-off
       from the carparking areas and the driveways shall have the first flush (the first 12 mm of rainfall or hose-
       down) collected in a grease/oil arrestor provided on site prior to being permitted to discharge into
       Council’s drainage system.
       All other clean stormwater, such as roof water, can be collected on site and discharged through a single
       underground drain line directly into the existing drainage system, bypassing the grease/oil arrestor.




A c:\docume~1\tblogg\locals~1\temp\bcl technologies\easypdf 5\@bcl@a4077865\@[email protected]

Used in these records

About this file

File size
60 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

06_2361 - SUPERSEDED Negotiated Decision Notice [As Published].pdf · 60 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.