Council archive · source document
Approved Document Construction Management Plan OPW25-0206 · OPW25/0206
Plans and drawings: the text below has words only, no drawings.
Incident Reporting
Reporting a Incident reporting is managed by:
hazard, injury Completing incident report forms if any hazard/injury/incident occurs, this
or incident includes near misses
Reporting incidents to site supervisors and SEMP Manager
Ensuring incident report forms are located in all vehicles accessing the site
Risk Assessment
Risk Risk is managed by a system of:
Management Workplace assessment
Hazard identification
Remedial action
Updating WHS
Documentation and reports that will be used in this process include:
Biodiverse Environmentals Job Safety analysis forms
Safe Work Method Statement - SWMS
Training and Induction
Documentation Training records will be maintained as evidence of training delivery and assessment
of competence
Generic WHS All staff have the skills and knowledge acquired from:
training General induction training
Using JSA forms
Risk specific Staff required to conduct activities with a specific health and safety risk have
WHS training completed relevant training for:
• First aid
Task specific Staff required to conduct activities with a specific health and safety risk have
WHS training completed training relevant to the project such as:
• Agricultural chemical use
• Chainsaw use
Appendix 3 – Pedestrian and Traffic Management Plan
Traffic matters and safety measures to be implemented
Traffic Management
Traffic If a formal traffic management plan is identified as being required for tree
Management Plan clearing works it will include the following:
i. a Traffic Management Control Plan in accordance with the Manual of Uniform
Traffic Control Devices (MUTCD) detailing all temporary signage and traffic
control measures prior to construction;
ii. maintenance of safe vehicle and pedestrian access for the areas affected by
the works during and after daily construction has ceased;
iii. proposed fencing to the site during the construction phase of the
development;
P.O. Box 320, Eudlo E. [email protected]
Queensland, 4554, P. 0408 011 584 | ABN 18 766 198 454
Australia www.biodiverse-environmental.com.au
FLORA | FAUNA | REHABILITATION | FIRE | WATER
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Approved Document Construction Management Plan OPW25-0206.pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.3 MB (small file)
- File type
No other editions are linked here.