iv. approval of the Traffic Management Control Plan by the Department of
Transport and Main Roads (DTMR) for any works on State controlled roads; and
v. provision for worker car parking.
Council owned land
Work on road Permission will be sought from the relevant local Council if work is to be carried
reserves or out on a road reserve or Council owned land
council owned
land
Deliveries
Deliveries to site Safety measures to be implemented to ensure deliveries to the site are
undertaken in a safe manner include:
• Locating the delivery drop off point/s so that delivery vehicles do have to
cross the site
• Delivery drop off points to be clearly marked
• Deliveries to be scheduled outside of peak traffic and pedestrian times in
the area
Emergency Vehicle Access
Ambulance or Measures to be implemented to ensure emergency vehicles movement is not
fire vehicle impeded include:
access • Notifying emergency services of any road or lane closures
Hours of Operation
General Hours of Access to site by construction vehicles must be carried out between the hours of
Operation 7am and 5pm Monday to Friday.
Peak Measures to be implemented to ensure periods of peak vehicle and pedestrian
traffic/pedestrian traffic in the area adjoining the site include:
hours • Limiting vehicle access to the site during peak pedestrian traffic in the area
specifically on a business day between 7am and 5pm.
• Limiting vehicle access to the site during peak vehicle traffic in the area
specifically on a business day between 7am and 5pm
Parking
Parking for Control measures to manage parking near and onsite include:
workers and site • RACV to provide staff and contractors with details of available parking sites
visitors (including a map if applicable) during works
• Staff to commute together, limiting vehicles onsite
• Heavy machinery to park within the project footprint
Pedestrian and Cyclist Management
Pedestrian and Safety measures to be implemented to protect the safety of pedestrians onsite
cyclist access to include:
and onsite • Designated clearly marked pedestrian only walkways that are kept clear
• Designating and clearly signing ‘no-go’ zones into the site
• Implementing safe work distances
• Ensuring all workers and visitors wear high visibility clothing onsite
Public Transport
Effects on public Not applicable – Neither the construction of the site or the resultant traffic are
transport expected to affect public transport services or access to public transport services
services
P.O. Box 320, Eudlo E. [email protected]
Queensland, 4554, P. 0408 011 584 | ABN 18 766 198 454
Australia www.biodiverse-environmental.com.au
FLORA | FAUNA | REHABILITATION | FIRE | WATER
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Approved Document Construction Management Plan OPW25-0206.pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.3 MB (small file)
- File type
No other editions are linked here.