Skip to the record
The gold standard in government transparency.

Original source · versioned page text

2015-06-23 Planning & Organisation Committee Meeting Agenda

of 123

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (12.7 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

PLANNING & ORGANISATION COMMITTEE MEETING AGENDA                                 23 JUNE 2015


RECOMMENDATION
That Council note the report by the Development Planner to the Planning & Organisation
Committee Meeting dated 23 June 2015 regarding Application No. REC15/0010 for a
Development Permit for Reconfiguration of a Lot – 1 lot into 2 lots situated at 38 Pavilion
Street, Pomona and:
A.   Approve the application in accordance with the following conditions:
           When Conditions Must Be Complied With
     1.    Unless otherwise stated, all works required by the conditions of this Decision
           Notice must be completed prior to submission of the subdivision plan to Council
           for compliance assessment.
           Approved Plans
     2.    Development undertaken in accordance with this approval must generally
           comply with the approved plans of development. The approved plans are listed
           in the following table unless otherwise amended by these conditions.
            Plan No.          Rev.          Plan/Document Name                     Date
            15-3836AB                Plan of Proposed Reconfiguration of Lot     16-03-15
                                     1 on RP196894, prepared by Max
                                     Watterson & Associates

           Performance Bond
     3.    Security in the form of a cash bond or trading bank guarantee to the sum of
           $5,000 must be submitted to Council, to secure performance of all conditions of
           this approval, prior to the issue of a Development Permit for Operational Works.
           The cash bond or trading bank guarantee will be returned on performance of the
           conditions of approval less any costs incurred by Council in respect of enforcing
           performance of this permit. Council reserves the right to call upon the bond or
           guaranteed sum to effect compliance with conditions.
           External Works
     4.    The north eastern corner of the intersection of Pavilion Street and Tree Street
           must be upgraded. The works must be undertaken in accordance with an
           Operational Works approval and must include in particular:
           a.    provision of kerb and channel at the intersection and extending a minimum
                 of 6 metres along the Pavilion Street and Tree Street frontages
           b.    any associated widening of the existing pavement including suitable tapers
                 in Pavilion Street and Tree Street.
           c.    runoff from the kerb and channel directed to the existing table drain in
                 Pavilion Street
           This condition is imposed pursuant to s665 of the Sustainable Planning Act 2009
           being non-trunk infrastructure.
     5.    To minimise the amount of surface runoff from the Tree Street road verge
           entering the site, minor regrading of the verge area must be undertaken. The
           works must be undertaken generally in accordance with drawing number 1511-
           02A prepared by Callghan and Toth dated May 2015. The works must be
           undertaken in accordance with an Operational Works approval.
           Stormwater Drainage
     6.    Stormwater runoff from proposed Lot 1 must be discharged into Council’s
           existing drainage system in Pavilion Street

                                                                                Page 43 of 123
Log in to download the original file

2015-06-23 Planning & Organisation Committee Meeting Agenda(PDF, 12MB).pdf · 12.7 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.