2007/1173
ecoaccess Bo
environmental licences and permits
Notice
Change to an existing approval
(a) The works (including any other associated works) have been constructed in accordance with the
approved drawings and these conditions;
(b) -The works:-
(i) are structurally adequate for anticipated usage; and
{ii) comply with all relevant codes including DERM’s operational policy, Building and
engineering standards for tidal works and prescribed tidal works; and
{c) The bed and banks of the waterway for a distance of 15 metres around the site of the works are
clear of all debris.”
11. The chief executive administering the Coastal Protection and Management Act 1995 may order the
works to be removed or modified, within a reasonable time, if the works have or are likely to have a
woe oe oe 2 ap
significant effect on coastai management because the works: + oe
7
(a) create a navigation hazard-or other danger to the public; or
(b) cause erosion or tand degradation; or
(c) are unstable or have not been constructed according to the approved plans.
3. Additional information for applicants
It is'a requirement of the Environmental Protection Act 1994 that if the owner or occupier of this site *
becomes aware a Notifiable Activity (as defined under Schedule 2 of the Environmental Protection Act 1994)
is being carried out on this land or that the land has been affected by a hazardous contaminant, they must,
within twenty two (22) business days after becoming aware the activity is being carried out, give notice to the
Department of Environment and Resource Management. A list of Notifiable Activities is provided within
Schedule 2 of the Environmental Protection Act 1994.
* This concurrence response pursuant to the integrated Planning Act 1997 and assessed against section 104
of the Coastal Protection and Management Act 1995 does not remove the need to obtain any further
approvals for this development which may be required pursuant to this or other legislation, both State and
Commonwealth. Applicants are advised to check with all relevant statutory authorities for such approvals as
may be required.
4. Additional information for. Assessment Manager
The Department of Environment and Resource Management referral agency jurisdiction for the development
application is confined to that aspect of the application involving the triggers identified in the response.
DERM has no referral agency jurisdiction in relation to other aspects of the development application.
In this regard It should be noted that the State Coastal Management Plan 2001 and SEQ Regional Coasta!
Management Plan 2006 which, for the purposes of making a statutory decision, has the same effect as a
state planning policy. The assessment manager is required to give due consideration to the relevant State
planning policies when deciding the application. : 7
Please note that it is a requirement under Section 3.5.15 of the Integrated Planning Act 1997 that a copy
of the final decision notice (which includes DERM's concurrence conditions) for this application issued by
the Council, be forwarded to each referral agency. Therefore, could please send a signed hardcopy
té DERM's EcoAccess Customer Service Unit, PO Box 15155 / EAST 4002 and an electronic copy
to [email protected] 4 of 9 - AD080109 Department of Environment and Resource Management
Page 14 of 21
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Letter - Change to an Existing Approval - 010.2007.00001173.03 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 837 KB (small file)
- File type
No other editions are linked here.