                               Noosa Shire Council
                          Charges Resolution (No.8) 2024



      ACROL    is the adopted charge rate for reconfiguring a lot stated in section 8.3
               (Council adopted charge rate).

      QROL     is the total no of lots.

      C        is the credit stated in section 8.4 (Credit).

      Note:

               (a) for residential lot reconfiguration, the adopted infrastructure charge
                   is apportioned across all networks;

               (b) for non-residential lot reconfiguration, the adopted infrastructure
                   charge apportionment excludes the stormwater charge component.
                   The stormwater charge will be calculated and issued on a
                   subsequent material change of use or building work approval when
                   the impervious area is able to be determined.

(2)   An infrastructure charge that may be levied for a material change of use or
      building work for residential development is generally calculated as follows:

      LCR = (Sum(ACR x QR) for each defined use) − C

      Where:

      LCR      is the infrastructure charge that may be levied for a material change of
               use or building work for residential development.

      ACR      is the adopted charge rate for each defined use for a material change of
               use or building work for residential development stated in section 8.3
               (Council adopted charge rate).

      QR       is the residential quantity for each defined use.

      C        is the credit stated in section 8.4 (Credit).

(3)   An infrastructure charge that may be levied for a material change of use or
      building work for non-residential development is generally calculated as follows:

      LC = LCNR + LCSW

      Where:

      LC       is the infrastructure charge that may be levied for the total development

      LCNR = (Sum of (AC4 x Q4) for each defined use) − C4

      LCSW = (ACSW x QSW) − CSW

      LCNR     is the infrastructure charge that may be levied for a material change of
               use or building work for non-residential development for the transport,
               public parks and land for community facilities networks.

      LCSW     is the levied charge for a material change of use or building work for
               non-residential development for the stormwater network.




                    Council Resolution effective 15 August 2024                            Page 36 of 90
Log in to download the original file

035d7187e5.pdf · 27.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.