2ND RFI - Attachment 4B - Response to Stormwater Issues ADG · MCU22/0118

of 2

Text shows just the words. Original shows the document exactly as it was published.

           Noosa Council
           PO Box 141
           TEWANTIN QLD 4565


           Attention: Patrick Murphy – Coordinator Planning

           Your Ref: MCU22/0118
           Our Ref: 22366 C L003
           13th July 2023
           RS /tm
           Sunshine Coast Office

           RE:   94 AND 142 NOOSA DRIVE, NOOSA HEADS QLD 4567, LOT 3 ON SP126203, LOT 0 ON
                 SP203417 & LOT 203 ON SP267424
                 APPLICATION REF: MCU22/0118
                 RESPONSE TO INFORMATION REQUEST


           On behalf of RACV Ltd, ADG Engineers provides the following civil engineering responses to the information
           request issued by Noosa Council on the 6th of April 2023, associated with 94 and 142 Noosa Dr, Noosa
           Heads (Lot 3 on SP126203, Lot 0 on SP203417 & Lot 203 on SP267424).

            INFORMATION REQUEST ITEM                    ADG RESPONSE

            1. UPDATE SWMP, MUSIC & PRELIMINARY ENGINEERING PLANS

            1.1 Provide geotechnical borehole and       Based on the In Situ Constant Head Permeability Test
                test results demonstrating that the     conducted by Tectonic Geotechnical & Environmental
                proposed ‘pipeless’ bioretention will   Engineers on 12.04.23, the MUSIC model for the post-
                function at the proposed location by    developed site has been updated with the newly derived
                providing the following for the         saturated hydraulic conductivity value as 115.00mm/hr within
                bioretention location: In-situ Soil     the 0.4m of the upper soil profile. It is confirmed that the 15L of
                classification, Groundwater level       water used to pre-soak the site has rapidly drained away within
                (BGL and mAHD), and In-situ             the existing sandy media proving the area suitable for a pipeless
                saturated hydraulic conductivity        bioretention basin. The test has confirmed the insitu soil
                test results at proposed level of       classification in this area as SAND, with organics and no ground
                bioretention base                       water presence up to 1.8m below ground level in the area where
                                                        the bioretention basin is proposed.

            1.2 Demonstrate that the In-situ            Refer to the Section 6 and Appendix H of attached Stormwater
                saturated hydraulic conductivity        Management Plan (22366 C R10 Rev05 13.07.2023) prepared
                results have been correctly applied     by ADG.
                to the MUSIC model. These rates
                should be applied as the
                bioretention design saturated hyd
                cond

            1.3 Provide updated plans showing the       The bio-retention basin size is increased to 60m2 area at
                spatial requirements for the            surface based on the new hydraulics conductivity value as per
                updated      (enlarged)  pipeless       the In Situ Constant Head Permeability Test conducted by
                bioretention system                     Tectonic Geotechnical & Environmental Engineers. Refer to
                                                        Appendix C of the Stormwater Management Plan (22366 C
                                                        R10 Rev05 13.07.2023) prepared by ADG, for updated plans,

BRISBANE / SYDNEY / MELBOURNE / GOLD COAST / SUNSHINE COAST / DARWIN / PERTH                        ABN 63 131 876 143
Full text of the other 1 page

Page 2

                                              22366_SK02_POST DEVELOPMENT-[05], and
                                              22366_SK03_BIORETENTION BASIN-PRELIMINARY
                                              DETAILS-[03].

 1.4 Provide details of the rainfall-runoff   Refer to the Appendix H of attached Stormwater Management
     and pollutant export parameters          Plan (22366 C R10 Rev05 13.07.2023) prepared by ADG.
     adopted for the source nodes in the
     MUSIC         modelling          (pre-
     development          and         post-
     development scenarios)

 1.5 Show how the rainwater tank              The overflow from rainwater tanks are proposed to be
     overflows and the runoff from the        conveyed using down pipes and discharge into bio basin area
     raised walkways will physically be       through localised 200mm deep vegetated swales, where the
     able to drain to the proposed            natural topography falls away from the discharge point. The
     bioretention device, as assumed in
                                              runoff from the raised timber walkway will fall directly to the
     the MUSIC model
                                              natural surface below, which as demonstrated has adequate
                                              exfiltration properties. In the post-developed MUSIC model, the
                                              timber walkway node is modelled using the parameters for
                                              existing vegetated surface as agreed by NSC Assessment
                                              Officer (Leon Rowland from Switchback Consulting on behalf
                                              of NSC). Further, it is not considered practical to capture water
                                              run-off from a raised timber walkway structure. The bio
                                              infiltration basin has been oversized to compensate for the
                                              water quality catchment area of the walkway structure.

We believe the above responses along with the supporting information adequately addresses the items
raised in Council’s recent correspondence. Should you wish to discuss further, please feel free to contact
me on the above details.

Yours sincerely,
ADG ENGINEERS (AUST) PTY LTD




RAWDON STANFORD
Associate Director - Civil




                                                                                                      Page 2 of 2

Used in these records

About this file

File size
212 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

2ND RFI - Attachment 4B - Response to Stormwater Issues ADG.pdf · 212 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.