2ND RFI - Attachment 4B - Response to Stormwater Issues ADG · MCU22/0118

of 2

Text shows just the words. Original shows the document exactly as it was published.

                                              22366_SK02_POST DEVELOPMENT-[05], and
                                              22366_SK03_BIORETENTION BASIN-PRELIMINARY
                                              DETAILS-[03].

 1.4 Provide details of the rainfall-runoff   Refer to the Appendix H of attached Stormwater Management
     and pollutant export parameters          Plan (22366 C R10 Rev05 13.07.2023) prepared by ADG.
     adopted for the source nodes in the
     MUSIC         modelling          (pre-
     development          and         post-
     development scenarios)

 1.5 Show how the rainwater tank              The overflow from rainwater tanks are proposed to be
     overflows and the runoff from the        conveyed using down pipes and discharge into bio basin area
     raised walkways will physically be       through localised 200mm deep vegetated swales, where the
     able to drain to the proposed            natural topography falls away from the discharge point. The
     bioretention device, as assumed in
                                              runoff from the raised timber walkway will fall directly to the
     the MUSIC model
                                              natural surface below, which as demonstrated has adequate
                                              exfiltration properties. In the post-developed MUSIC model, the
                                              timber walkway node is modelled using the parameters for
                                              existing vegetated surface as agreed by NSC Assessment
                                              Officer (Leon Rowland from Switchback Consulting on behalf
                                              of NSC). Further, it is not considered practical to capture water
                                              run-off from a raised timber walkway structure. The bio
                                              infiltration basin has been oversized to compensate for the
                                              water quality catchment area of the walkway structure.

We believe the above responses along with the supporting information adequately addresses the items
raised in Council’s recent correspondence. Should you wish to discuss further, please feel free to contact
me on the above details.

Yours sincerely,
ADG ENGINEERS (AUST) PTY LTD




RAWDON STANFORD
Associate Director - Civil




                                                                                                      Page 2 of 2

Used in these records

About this file

File size
212 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

2ND RFI - Attachment 4B - Response to Stormwater Issues ADG.pdf · 212 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.