21. All fill, associated batters and retaining structures (both above ground and below ground)
must be contained entirely within the subject site unless written permission from the
respective landowner(s) is provided to Council. All earthworks must be undertaken in
accordance with the provisions of Australian Standard AS3798: Guidelines on Earthworks
for Commercial and Residential Developments.
22. All retaining walls must be designed and constructed in accordance with the planning scheme
and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
safety fence.
Construction Management Plan
23. A Construction Management Plan must be submitted to and approved by Council prior to the
issue of the Building Permit. The plan must include but not be limited to the following:
a. traffic management during all aspects of the construction phase including:
i. a Traffic Management Control Plan in accordance with the Manual of Uniform
Traffic Control Devices (MUTCD) detailing all temporary signage and traffic
control measures prior to construction
ii. maintenance of safe pedestrian access for the areas affected by the works during
and after daily construction has ceased
iii. proposed fencing to the site during the construction phase of the development
iv. provision for worker car parking
b. maintenance and protection of water quality and existing drainage lines through the
construction site, through the implementation of appropriate erosion and sediment
control measures
c. works programme identifying key components of the works and their respective
durations
d. establishment of a communication protocol with the general public, adjoining owners,
emergency services and local businesses to advise of agreed construction times,
impacts on traffic, services and other relevant issues
e. identification of complaint management procedures including:
i. contact details for the on-site manager
ii. dispute resolution procedures
f. details on the location of external fill/dump sites/sources, the haulage route, type of
vehicle to be utilised during filling operations and frequency of usage. NB any damage
to the existing road system as a result of haulage operations shall be fully repaired at
the applicant’s expense
Damage to Services and Assets
24. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
5. REFERRAL AGENCIES
Not applicable.
Page 4 of 7
Document Set ID: 20593167
Version: 3, Version Date: 04/06/2018 Print Date: 4 June 2018, 10:10 AM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Council DA Decision Notice - CCB31435-10A9-417B-A5FD-7E0B3B229384.pdfRelated documentApplication case desk ↗
About this file
- File size
- 11.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.