ORDINARY MEETING MINUTES                                                            19 MAY 2022


        5.    All works must be undertaken in accordance with Maritime Safety Queensland
              (MSQ) and Department of Agriculture and Fisheries (DAF) requirements relating
              to signage and aids to navigation as detailed in the Noosa Oyster Restoration
              Project – Project Restoration Plan (Section 7) prepared by The Nature
              Conservancy dated January 2022.
        6.    All works must be undertaken in accordance with DAF requirements relating to
              notifications, marking of approved boundary areas and restoration of marine
              plants/tidal profiles that are temporarily impacted as a result of the works as
              detailed in the SARA Decision Notice.
        7.    All works must be undertaken in accordance with Best Practice Erosion and
              Sediment Control (BPESC) guidelines for Australia (International Erosion Control
              Association).
        8.    All works must be undertaken in accordance with Sections 6.1 and 6.4 of Noosa
              Oyster Ecosystem Restoration Project - Project Restoration Plan prepared by The
              Nature Conservancy Australia dated January 2022.
        9.    All works must be undertaken in accordance with the current Queensland Acid
              Sulfate Soil Technical Manual: Soil management guidelines, prepared by the
              Department of Science, Information Technology, Innovation and the Arts, 2014.
        10.   All materials used for construction works must be clean materials to ensure that
              the works do not contaminate the waterway.
        11.   All structures must be designed and constructed such that they are free standing
              within the waterway and are not connected to or behind the revetment wall.
        12.   All structures must have no detrimental effects on stormwater drains and/or
              easements.
        13.   In the event of collapse or failure of structural integrity of the oyster restoration
              substrates, the works must be removed from the waterway or reconstructed in
              accordance with this development approval.
        14.   All works must be undertaken in accordance with an approved Construction
              Environmental Management Plan (CEMP) which consolidates the commitments
              and management measures described in the Noosa Oyster Ecosystem
              Restoration Project – Project Restoration Plan including, but not limited to:
              a.    A Site Management Plan which describes environmental management
                    measures at the proposed load out site including details of stockpile
                    management;
              b.    An Erosion and Sediment Control Plan (ESCP) in accordance with BPESC
                    guidelines;
              c.    A Marine Plant and Water Quality Monitoring Plan designed to monitor the
                    composition of marine plant assemblages at habitat restoration sites and
                    appropriate sites upstream and downstream; and
              d.    A Marine Biosecurity Management Plan for construction vessels.
              The CEMP should be submitted to Council for approval 20 business days prior to
              the commencement of works.
        15.   A monitoring report must be provided to Council on a six-monthly basis for the first
              year (and annually for the following 4 years) following completion of construction
              works which details the results of restoration monitoring and evaluation, including
              adaptive management measures taken and the success or otherwise of those
              measures.
        16.   Upon completion of construction works, any construction debris or waste must be
              removed from site and disposed of appropriately.

                                                                                  Page 15 of 20
Log in to download the original file

2022-05-19 Ordinary Meeting Minutes(PDF, 432KB).pdf · 442 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.