5.2 Proposed Design
5.2.1 External Catchment
Runoff from the External Catchment area currently flows through the Development Area.
It is proposed to capture the flows (including up to 1%AEP design flows) from the External Catchment area and
pipe it through the Development Area and discharge to the existing infrastructure.
Refer to Appendix C for the concept stormwater layout.
5.2.2 Development Area
A new internal stormwater pit and pipe drainage system with a detention basin is proposed for the Development
Area. The proposed system will discharge to the existing stormwater infrastructure within the Development Area
and the existing Bunnings Site.
The piped flows from the External Catchment area will bypass the detention basin.
Refer to Appendix C for the concept stormwater layout sketch for the development.
5.2.3 Detention System
The following table summarises the proposed detention system characteristics:
Table 3 – Detention Basin Details
Detention Basin Parameters
Minimum surface area of the base of the basin (m2) 150
Lowest Invert Level (m AHD) 9.100
1% AEP Storage Level (m AHD) 9.980
Minimum detention volume at 1% AEP storage level (m3) 132
Low Level Orifice Control 1 x 225mm dia @ IL 9.100 mAHD
High Level Weir Control 3.6mm wide @ IL 9.900 mAHD
Further refinement of the detention system location, layout, sizing and outlet configuration will need to be
undertaken as part of detailed design and after revised detailed survey has been received.
BR210522_SBSMP_Rev3.docx Page 10 of 25
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.