5.1 Pre- and Post-Development Design Flow Rates (unmitigated)
The table below, provides a summary of the pre-development design flow rates off the Development Area only
calculated using DRAINS:
Table 2 - Comparison of Pre- and Post-Development Design Flow Rates
Q1 Q2 Q5 Q10 Q20 Q50 Q100
Area
(63% AEP) (50% AEP) (20% AEP) (10% AEP) (5% AEP) (2% AEP) (1% AEP)
(ha)
(m3/s) (m3/s) (m3/s) (m3/s) (m3/s) (m3/s) (m3/s)
External Catchment Only
External
Catchment 0.735 0.168 0.227 0.313 0.365 0.434 0.531 0.585
Development Area Only
Development Area
0.415 0.059 0.089 0.115 0.140 0.167 0.198 0.222
(Pre-Development)
Development Area
0.415 0.124 0.161 0.207 0.242 0.279 0.327 0.363
(Post-Development)
Increase 0.063 0.072 0.082 0.096 0.109 0.126 0.141
(+49%) (+55%) (+63%) (+60%) (+61%) (+61%) (+61%)
Results show that, compared to pre-development design flow rates, without mitigation, there is an increase in
post-development flow rates off the Development Area.
BR210522_SBSMP_Rev3.docx Page 9 of 25
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.