NOOSA COUNCIL Capital Schedule
for the period ending 30 June 2021
Report run date: 05-Jul-2021 13:56:56
Total Parks & Playgrounds 780,000 1,139,554 1,224,554 1,705,000 1,705,000 1,702,303 3,076,538 99.88%
500622 500636 500622 - Noosa Heads Noosa Parade Road Corridor Upgrade - Design 0 0 oO 100,000 100,000 217,463 193,549 21746%
500888 501039 500888 - Cooroy Maple Street Raised Pedestrian Crossing - LGGSP 347,000 347,000 347,000 347,000 347,000 28,285 7,[email protected]%
500903 500806 500903 - Tewantin, Hilton Terrace CNLGGP & Iwory Palms 0 6,568 231,865 231,865 231,865 161,956 [email protected]%
500919 500823 500919 - Wallace Park Pathway 5&6 - W4Q 119,000 119,000 119,000 119,000 119,000 110,301 [email protected]%
500056 501033 500856 - Shire Pathway Renewal Program Annual - W4Q 332,000 332,000 332,000 332,000 332,000 370,682 18.850 111.65%
500967 500084 500967 - Noosaville Sea Eagle Drive & Shire Drive Pathway Upgrades 195,000 358,137 358,137 358,137 358,137 181,719 3.1916 50.74%
510037 501032 510037 - Noosa Heads Main Beach Boardwalk LED Lighting Renewal 120,000 120,000 120,000 120,000 120,000 80.384 0®@ 58.37%
510050 501049 510050 - Peregian Beach Boardwalk - USR oO 230,000 230,000 230,000 230,000 177.561 21.7510 77.20%
510051 501050 510051 - Noosa Heads Sunshine Beach Road Pathway Lighting - U&R oO 150,000 150,000 150,000 150,000 145,896 00 97.26%
Total Pathways & Boardwalks 41,113,000 1,662,705 1,888,002 1,988,002 1,988,002 1,474,256 329,538 T4 16%
510048 ana 510048 - Public amenities renewal and upgrade works - U&R 0 220,000 220,000 220,000 220,000 173,279 06 78.76%
Total Public Amenities 0 220,000 220,000 220,000 220,000 173,279 0 78.76%
500857 501021 500957 - Shire Bus Shetter Disabled Compliant Program Annual - PTIAP 250,000 250,000 250,000 250,000 250,000 119.448 80.413 47.78%
Total Public Transport Infrastructure 250,000 250,000 250,000 250,000 250,000 119,448 89,413 47.78%
‘500757 500840 500757 - Black Mountain - Road Priority Sections and Road Reconstruct 0 0 0 0 0 213 te 0.00%
500959 501035 500959 - Shire Reseal & Rehabilitation Renewal Program Annual 3,091,726 3,091,726 3,091,726 4879537 4879537 4,585,078 326,734 © 93.07%
510017 510017 510017 - Damaged Guardrail Renewals (Various) oO 25,768 25,768 25,768 25.768 25.545 00 98.13%
510022 510022 510022 - Sunrise Beach, Tingira Cres Emergent Slip Repair 0 0 0 0 0 5.405 [email protected]%
510025 510025 510025 - Sunshine Beach, Ross Cres Emergent Slip Repair Qo 0 0 o o 18,233 06 0.00%
510038 501034 510038 - Shire Sealed Road Network Rehabilitation and Reconstruction 790,000 790,000 790,000 0 oO 0 06 0.00%
510047 501045 510047 - Tewantin Bypass Stage 1 0 600,000 600,000 600,000 600.000 460,079 [email protected]%
Total Sealed Roads Network 3,881,726 4,507,494 4,507 494 5.505.305 5,505,305 5,094,553 695,089 92.54%
510063 501061 510063 - Tewantin Netball Courts Upgrade - U&R 0 310,000 310,000 310,000 310,000 319,140 0 > 102.95%
Total Sports Ground and Facilities 0 310,000 310,000 310,000 310,000 349,140 0 102.95%
‘Stormwater Drage
500916 500916 - Gympie Terrace Stormwater 600,000 600,000 40,000 40,000 40,000 6.311 [email protected]%
500960 s500888 500960 - Shire Bioretention Basin Renewals Program Annual 0 72,190 72,190 72.190 72,190 9.557 25650 13.24%
500872 500802 500972 - Noosaville, Project Ave Stormwater Drainage Easement Upgrade 200,000 237,324 237 324 85,000 85,000 21,018 00 24.73%
510039 501036 10039 - Sunrise Beach Sobraon Street Slope Stabilisation - W4Q &LRCI 915,346 915,346 915,346 915,346 915,346 230,057 273,[email protected]%
510080 510080 510080 - Marcus Beach DLW Stormwater Culvert Emergent Works 0 0 0 266.210 266.210 117,962 57,[email protected]%
Page 31 of 69See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.