SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 10 AUGUST 2021
Page 32 of 69
NOOSA COUNCIL Capital Schedule
for the period ending 30 June 2021
Report run date: 05-Jul-2021 13:56:56
Total Stormwater Drainage 1,715,346 1,824,860 1,264,860 1,378,746 1,378,746 394,804 333,528 28.64%
500546 500546 500546 - Whole of Shire Forward Planning & Design Program - Construct 500,000 500,000 500,000 420,000 420,000 264.419 412770 62.06%
500679 500679 500679 - Tewantin, Hitton Tce & Emest St Intersection Upgrade Constr oO 1,365,597 1,435,507 1435597 1,435,507 1,436,107 08 100.04%
500893 500883 500893 - Sunshine Beach Pacific Avenue Pathway, Pedestrian & Drainage 0 24,608 24,608 24,608 24,608 9.813 06 39.88%
500873 501000 500973 - Transport Strategy. Walking & Cycling Strategy &CNLG Grant oO 250,406 250,406 250.406 250.406 201,176 32,[email protected]%
510083 510083 510083 - Noosa Heads Bus Station Options Analysis and Concept Design oO oO oO oO 0 1,022 00 0.00%
Total Transport and Infrastructure Management 500,000 2,140,704 2,210,701 2,130,704 2,130,704 1,912,537 76,763 89.76%
500874 501001 500874 - Noosa Heads “The Woods” Bin Storage Enclosure 0 58.457 58.457 58.457 58.457 17,381 [email protected]%
500976 501003 500976 - Masterplan Landfill SW Controls & Design 0 115,466 115,466 115,466 115,466 26,500 18,[email protected]%
510028 510028 510028 - lllegal Dumping Hotspot 0 50,433 50,433 50.433 50,433 44,000 [email protected]%
510042 501040 510042 - Noosaville Eumundi Road Landfill Outbound Weighbndge 560,000 560,000 560,000 80,000 80,000 26.115 40 32.64%
510043 501041 510043 - Noosaville Eumundi Road Landfill Liner, Cell capping design 2,110,000 2,110,000 2,110,000 200,000 200,000 175,148 [email protected]%
510044 501042 510044 - Noosaville Eumundi Road Landfill Expansion of Resource Recov 750,000 750,000 750,000 50,000 50,000 6.857 10,800 © 13.71%
Total Waste Management 3,420,000 3,653,356 3,653,356 363,356 563,356 296,392 71,194 52.72%
500686 501044 500686 - Shire Bridge Annual Level 3 Inspections Annual 55,000 55,000 55,000 55,000 55,000 41341 10,[email protected]%
500753 500753 500753 - Zero Emissions Noosa Project implementation 250,000 521,655 521,655 521,655 521,655 417,167 [email protected]%
500963 500001 500963 - Shire CCTV Drainage Condition Assessment Program Annual 220,000 220,000 220,000 220,000 220,000 163,231 6230 74.20%
500964 500882 500964 - Shire Road Infrastructure Asset Data Mgt & Condition Annual 220,000 340,000 340,000 340,000 340,000 229,084 06 67.64%
500877 501004 500977 - Asset Management Systems Implementation 200,000 200,000 200,000 200,000 200,000 86.272 00 43.14%
510020 510020 510020 - Noosa Junction Streetscape oO 46,000 46,000 46,000 46,000 10.978 13,[email protected]%
Total Asset Management 945,000 1,382,655 1,382,655 1,382,655 1,382,655 948,974 102,083 68.63%
500518 500518 500518 - Plant and Fleet Replacement Program 895,000 1,344,345 1,234,345 1,234,345 1,234,345 340.411 300,[email protected]%
Total Fleet - Plant Replacement 895,000 1,344,345 1,234,345 1,234,345 1,234,345 340,411 300,605 27.58%
500542 500542 500542 - implementation of Cl Anywhere Functionality for TechnologyOn 628,000 713,000 713,000 713,000 713,000 416,676 [email protected]%
Total Information Technology 628,000 713,000 713,000 713,000 713,000 416,676 68,504 38.44%
510045 501043 510046 - QTC Capital Debt Redemption 2,414,000 2,414,000 2,414,000 2.414.000 2.414.000 2,414,000 0 > 0.00%
Total Other 2,414,000 2,414,000 2,414,000 2,414,000 2,414,000 2,414,000 0 100.00%
Page 32 of 69See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.