Car Parking
27. Carparking shall be provided within the site generally as shown on drawing number 07025SK1(c) dated
27 August 2007 by Agenti Architects, except as modified herein.
28. A minimum of 4 covered carpark spaces shall be provided on site.
29. The carparking area shall be designed to comply with the provisions of AS/NZS 2890.1-2004 for user
class 1A with allowance for vehicles to enter and leave the site in a forward gear and with a minimum
head clearance (headroom) at any point of 2.2m.
30. All carparking shall be kept, maintained and line-marked in a condition fit for use.
Frontage Works
31. Footpath improvements such as topsoiling, grassing, and tree planting are required to the Attunga
Heights frontage of the site in accordance with Planning Scheme Policy PSP03 Landscaping Plants &
Guidelines. Grass shall be couch, free of weeds.
32. A new 1.5m wide concrete path shall be constructed along the Attunga Heights frontage of the site in
accordance with Council’s design standards and to an alignment that protects any significant vegetation
or any underground services.
33. All paths, driveways and parking areas shall be designed and constructed to ensure pedestrian safety
using non-slip materials, to produce an evenly graded surface finish, and to be in accordance with the
Disability Discrimination Act 1992 and Australian Standard 1428.1 Design for Access & Mobility.
34. All redundant vehicular crossings to the site shall be removed and replaced by kerb & channel, footpath
paving and landscaping such as trees and grasses in accordance with Council’s Standard specifications
prior to commencement of the use permitted by this permit.
Roof Water & Stormwater Drainage
35. Roof runoff from any new dwelling shall be directed to a rainwater storage system or tank (minimum
storage 3000 litres per dwelling/unit) that is installed to ensure water from the tank is used for external
uses (such as watering gardens, irrigation, ornamental ponds, water features, topping-up swimming pools,
outdoor cleaning, etc) and for use in flushing of toilets internal to the dwelling. All rainwater tanks are to
be designed and installed in accordance with the Queensland Development Code (QDC), Part 25 –
Rainwater Tanks, and shall be part of the plumbing application in conjunction with the building approval.
The location and capacity of the tanks shall be clearly shown on the plans submitted for Building Works /
Operational Works approval and any overflow shall be directed to the stormwater drainage system.
36. All stormwater drainage (including roof water overflow from the rainwater storage system) shall be
collected and discharged so there is no net increase in stormwater runoff from the site. Stormwater
drainage permitted to drain from the site shall be discharged to Council’s kerb & channel street drainage
system in Attunga Heights. Plans of the drainage design shall be prepared by a Registered Professional
Civil Engineer and submitted to Council prior to obtaining a Development Permit for Operational Works.
The maximum discharge of stormwater drainage allowable to Council’s kerb & channel street drainage
system at any one location is 25 litres/second.
37. To ensure that polluted run-off does not enter Council’s stormwater drainage system, stormwater run-off
from the carparking areas and the driveways shall have the first flush (the first 12 mm of rainfall or hose-
down) collected in a grease/oil arrestor provided on site prior to being permitted to discharge into
Council’s drainage system.
All other clean stormwater, such as roof water, can be collected on site and discharged through a single
underground drain line directly into the existing drainage system, bypassing the grease/oil arrestor.
To this end, a detailed maintenance plan shall be prepared for the proposed grease/oil arrestors, which
shall be submitted to the Council for approval prior to obtaining a Development Permit for Operational
Works.
The approved maintenance plan shall be incorporated in the Community Management Scheme for the
development and a copy of this shall be provided for Council’s records prior to commencement of the
approved Use.
A Development Permit for Building Works shall not be granted until a Development Permit for Operational
Works has been issued in regard to the drainage scheme.
38. All site stormwater drainage shall be by means of a gravity system.
AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@700946e8\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED Decision Notice - 010.2007.00000616.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 58 KB (small file)
- File type
No other editions are linked here.