Printed: Tuesday, 18 February 2014 STAGE
Scope & Brief Development
Design Review
Issues Status
Construction
Procurement
Finalisation
%complete
Handover
Design
Project Project Work Order
Project Description Staff Allocated Staff task updates
Budget Coordinator Number
SEALED ROAD NETWORK
$500,000 Annual sealed road renewal and rehabilitation program Allan Hull 0000025 <5% Allan Hull Currently scoping projects along David Low Way, Cooroy-Noosa Road, Gibson Road, Noosa Parade
$60,000 Sealed road pavement surveys and investigations Bryan Oconnor 0000026 <5% Bryan O'Connor Network pavement investigations to be commissioned shortly.
SPORTS GROUNDS & FACILITIES
10% Dallas Bickley Light pole to be removed by community group. Awaiting all quotes for 6x9 storage shed. Contractor for concrete pitch & synthetic turf
$30,000 Noosa District Sports Complex (Cricket Oval) Dallas Bickley 0000004
engaged. Slab pour scheduled for 18 March.
STORMWATER DRAINAGE
$50,000 Daintree Estate - Flood mitigation planning and design Adam Britton 0000027 5% Adam Britton Waiting on outcome of flood model review prior to seeking details for mitigation options.
Bryan O'Connor Reviewing initial investigations
15% Michael Cuthbert Review of pipe CCTV. Commenced onsite investigations and review of current designs / information. Pipe cleaning in progress.
$25,000 Gympie Terrace pipe rehabilitation - investigation and design Michael Cuthbert 0000005
Seeking advice for alternative rehabilitation options.
5% Adam Britton Met with consultants Projex Partners & Hydrology. Soon to issue request for information regarding performance indicators for
$50,000 Rifle Street Pomona - Flood mitigation planning and design Adam Britton 0000028
mitigation options.
$25,000 Seaview Creek - open drain civil works Adam Britton 0000029 10% Mara Ellis Public consultation completed. Designs 90% complete. Consultant to complete designs by 28 Feb. Civil works mid March. Planting
late March.
$75,000 Stormwater replacement program (non pipe work) Allan Hull 0000030 20% Allan Hull 6 pits completed as at 5 Feb. Estimated expenditure to date $34,000
STREETSCAPES & ROAD CORRIDORS
Cooroy - Noosa Road (St Andrews Drive - Gyndier) Adam Britton 0000031 0% Scott Morgan Preparing scope document for Transport Infrastructure Management requirements
$50,000 Mara Ellis Schedule design to commence March
Noosa - Eumundi Road (Eenie Ck - Walter Hay) Adam Britton 0000031 5% Scott Morgan Scope document for Transport Infrastructure Management requirements issued 10 Feb
Mara Ellis Schedule design to commence March
TRANSPORT & INFRASTRUCTURE MANAGEMENT
$8,000 Eenie Creek road / Langura Street Intersection safety upgrades Adam Britton 0000032 <5% Scott Morgan Preparing scope document for Transport Infrastructure Management requirements
Mara Ellis Waiting on scope document
$15,000 Eenie Creek road / Walter hay Drive Intersection safety upgrades Adam Britton 0000033 <5% Scott Morgan Preparing scope document for Transport Infrastructure Management requirements
Mara Ellis Waiting on scope document
$125,000 Weyba Road / Reef Street intersection improvements PIP Adam Britton 0000034 5% Scott Morgan Preparing scope document for Transport Infrastructure Management requirements
Mara Ellis Currently reviewing SCC design.
CARRY OVER PROJECTS
Kin Kin Entry Statement Dallas Bickley 100% Dallas Bickley Work complete
Cooroy Mill Signs Dallas Bickley 100% Dallas Bickley Work complete
25% Currently under negotiation Dallas Bickley
Project on hold until after groyne repairs. Requires MOU for Coastguard memorial arrangement prepared by Community Services.
Noosa Spit Interpretive Signage Dallas Bickley with Coastguard
Seeking advice from CEO / Mayor
Noosa Junction South Bound Bus Shelter Dallas Bickley 85% Dallas Bickley Works in progress, due for completion 28 Feb.
FUTURE PROJECT INVESTIGATIONS
Noosa Heads Park Road & Main Beach Boardwalk Adam Britton 0% Adam Britton Collating background information. Discussions with SCRC project officer.
5% Adam Britton Reviewing files & background info from Main Roads. Sought additional information from consultants Hydrology. Set up meeting with
Cooroy Road Flooding investigations Adam Britton
DTMR regarding mitigation options associated with Bruce Highway upgrade.
No risks present
Issues to be addressed
Significant risks
23
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.