2014-02-25 Infrastructure & Services Committee Meeting Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
NOOSA COUNCIL - PROJECT DESIGN & DELIVERY 2013-2014
Printed: Tuesday, 18 February 2014 STAGE
Scope & Brief Development
ATTACHMENT 1
Design Review
Issues Status
Construction
Procurement
Finalisation
%complete
Handover
Design
Project Project Work Order
Project Description Staff Allocated Staff task updates
Budget Coordinator Number
BRIDGES
$10,000 Forward planning for bridge rehabilitation program Bryan OConnor 0000006 5% Adam Britton In process of developing request for quote for level 3 inspections for Doonella, Witta Circle, Sheraton bridges.
Bryan O'Connor Need to review inspection schedule for all bridges
$250,000 Noosa Parade Munna Point bridge - Investigations and preventative works Adam Britton 0000007 10% Adam Britton Pile cap & pile cleaning works in progress as tides suit.
Tod Consulting Engineers currently reviewing previous reports and developing strategies
Concrete chloride testing completed. Results due late Feb.
Tod Consulting Engineers requested to consider if load limit required ahead of repairs
COASTAL, CANALS & WATERWAYS
$45,000 David Low Way, Beach Access 49 refurbishment Dallas Bickley 0000008 15% Dallas Bickley Bridge crew programmed works for 1st March.
$50,000 Gympie Terrace and William Street revetment wall and pathway rehabilitation Bryan OConnor 0000009 10% Project may be impacted Dave Shing Remediation of revetment wall options provided by Coastal Engineering consultants. Have consulted with jetty owner with a letter of
upon by jetty owner proposal to be provided to Council with expectation that owner is wanting to sell permit to occupy to Council.
negotiations
$50,000 Munna Point Holiday Park shoreline protection - design Bryan OConnor 0000010 10% Dave Shing International Coastal Management soon to provide options analysis.
$20,000 Noosa Dog Beach Shoreline Erosion Management Plan Coastal Monitoring Bryan OConnor 0000011 80% Dave Shing University Sunshine Coast monitoring (ongoing). Monitoring received and currently under review with Department of Environment
and Heritage Protection
$100,000 Noosa River Mouth groyne and rock wall rehabilitation Bryan OConnor 0000012 10% Dave Shing Rock sourced. Proposal includes 5tonne rocks and use of 50tonne excavator. Works scheduled for 18 February, duration 3 weeks.
Project news issued to Hasting St Assoc.
$1,300,000 Noosa Waters revetment walls rehabilitation Adam Britton 0000003 20% Adam Britton Works in progress. Stage 1 works complete. Critical sections of Stage 2 in Western lake completed. Advice to residents issued.
Contractor now operating in eastern lake section.
Additional geotechnical testing completed.
COMMUNITY FACILITITES
$15,000 Peregian Surf Life Saving Club Public Amenities - Planning & Design Dallas Bickley 0000013 0% Dallas Bickley Scheduled to be scoped in March.
HOLIDAY PARKS
$90,000 Noosa North Shore Beach Campground - Upgrade Septic Treatment System Allan Hazell 0000014 5% Allan Hazell Request for quote issued 14 Feb. Works scheduled to be completed prior to Easter holidays 7 April
(plumbing services)
PARKS & PLAYGROUNDS
$34,000 Cooroy Skate Park Refurbishment Dallas Bickley 0000001 0% Dallas Bickley Scoping scheduled to be attended to in March.
5% Dallas Bickley Glenda Cassidy (Parks) to provide audit / condition rating to determine works required. Following audit, quotes to be sought.
$50,000 Gympie Tce Furniture Refurbishment Dallas Bickley 0000015
Propose to take to Council for discussion on 25 Feb.
$12,000 Pomona Community House BBQ Relocation Dallas Bickley 0000016 <5% Dallas Bickley Initial scoping commenced.
$30,000 Noosa Heads Lions Park New Shower Dallas Bickley 0000002 5% Dallas Bickley Concept designs prepared. Consultation with user groups to occur late Feb. Memorial to be relocated.
$30,000 Peregian Beach Playground Refurbishment Dallas Bickley 0000017 10% Dallas Bickley Works scheduled to occur 17 March. Duration 4 weeks.
PATHWAYS & ENABLING FACILITIES
$30,000 Charles Street, Cooran pathway improvements Adam Britton 0000018 15% Adam Britton Design review process completed
Mara Ellis In design phase. Expect drawings ready 28 Feb
$100,000 Station Street, Pomona pathway improvements Adam Britton 0000019 5% Adam Britton Design review process completed
Mara Ellis In design phase. Expect drawings ready 28 Feb
Further consultation with school Principal required
$20,000 Weyba Creek Boardwalk rehabilitation stage 1 Dallas Bickley 0000020 <5% Dallas Bickley DPearce has scoped. Scheduled for approx. end March.
Gibson Road (Eumundi Noosa Rd to Thomas St) - On road cycle and pedestrian <5% A Britton Collate document for outsourcing design once scope documents provided.
$440,000 Adam Britton 0000021
improvements
Scott Morgan Preparing scope document for Transport Infrastructure Management requirements
Mara Ellis Prepare design brief for outsourcing.
$90,000 Sunshine Beach State School safety improvements Adam Britton 0000022 <5% Scott Morgan Scope document for Transport Infrastructure Management provided
Mara Ellis Draft design to Design Review meeting 21 Feb
PUBLIC TRANSPORT INFRASTRUCUTRE
40% Michael Cuthbert Fabrication programmed to commence off site early Feb completed onsite early March.
$25,000 Noosa Junction Mini Bus Shelter - Panels for weather protection Michael Cuthbert 0000023
22
<5% Clarify issues in design and Mara Ellis Clarify issues regarding design provided by SCC - Issue queries to GHD.
$300,000 Noosa Parade Transit Hub - Stage 1. Allan Hull 0000024
transit hub intent
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.