Decision Notice OPW21-0063
Plan No. Rev. Plan/Document Name Date
20651-C1000 C Locality Plan, Drawing Index & General 03 June 2021
Notes as prepared by Tod Engineers and
Project Managers
20651-C1100 C General Arrangement, Cross Sections & 03 June 2021
Details as prepared by Tod Engineers and
Project Managers
CURRENCY PERIOD
2. The Currency Period for this development approval lapses if the development has not
substantially started by 05 July 2023, unless an application to extend the currency period is
approved by Council.
SITE SPECIFIC CONDITIONS
3. The bridging style crossover is to be constructed generally in accordance with the approved
plan 20651-C1100 Rev C (as prepared by Tod Consulting) and must have sufficient
clearance to allow debris to be cleaned out so as to not block the flow of water in the channel.
GENERAL CONDITIONS
Engineering
4. A condition report including photographs of the frontage of the site must be completed and
submitted to Council at the prestart meeting.
5. The principal contractor must have all the appropriate insurance and public liability
documentation to carry out the works. The principal contractor is also responsible to ensure
that any subcontractors also have the appropriate insurance and public liability
documentation. Certificates demonstrating currency of public liability insurance and works
insurance covering the works must be submitted to Council prior to the prestart meeting.
6. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Civil engineering works.
7. A Construction Management Plan must be submitted to Council prior to the pre-start meeting
and must specifically address the following:
a. Traffic Management during the construction phase;
b. Appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
Devices (MUTCD); and
c. Provision for safe pedestrian access across the frontage of the site both.
8. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
Clearing of Vegetation
9. Prior to felling or pruning, all trees are to be inspected for wildlife (i.e. koalas, possums, birds’
nests etc.). If wildlife is present, the tree must not be felled or pruned until the wildlife has left
the tree or has been removed by a qualified person*. *(Refer to Advisory Note)
10. Vegetation removal or pruning must be undertaken in a manner that avoids damaging
surrounding vegetation and habitat.
11. All approved cleared vegetation must be disposed of lawfully.
12. Vegetation removal, felling and lopping must result in the area being stabilised against
erosion and turfed.
Page 2 of 7