2411-43615 SRA
Attachment 1—Referral agency conditions
(Under section 56(1)(b)(i) of the Planning Act 2016 the following conditions must be attached to any development
approval relating to this application) (Copies of the documents referenced below are found at Attachment 5)
No. Conditions Condition timing
Development Permit: Material change of use
10.9.4.2.4.1 – Material change of use near a state transport corridor—The chief executive
administering the Planning Act 2016 nominates the Director-General of the Department of Transport
and Main Roads (DTMR) to be the enforcement authority for the development to which this
development approval relates for the administration and enforcement of any matter relating to the
following conditions:
Stormwater management
1. (a) Stormwater management of the development must not cause (a) At all times
worsening to the operating performance of the state-controlled
road, such that any works on the land must not:
i. create any new discharge points for stormwater runoff
onto the state-controlled road
ii. concentrate or increase the velocity of flows to the state-
controlled road
iii. interfere with and/or cause damage to the existing
stormwater drainage on the state-controlled road
iv. surcharge any existing culvert or drain on the state-
controlled road
v. reduce the quality of stormwater discharge onto the
state-controlled road
vi. impede or interfere with any overland flow or hydraulic
conveyance from the state-controlled road
vii. reduce the floodplain immunity of the state-controlled
road.
(b) Prior to obtaining
(b) Submit RPEQ certification with supporting documentation to the development approval
North Coast Region, Development Assessment Team, via
for operational work or
[email protected], within DTMR, confirming that
the development has been designed in accordance with part (a) building work,
of this condition. whichever occurs first
for the relevant stage
(c) Submit RPEQ certification with supporting documentation to the
North Coast Region, Development Assessment Team, via (c) Within 20 business
[email protected], within the DTMR, confirming
days of the completion
that the development has been constructed in accordance with
parts (a) and (b) of this condition. of works
Vehicular Access onto the state-controlled road
2. (a) Road access is located generally in accordance with Site Plan, (a) At all times
prepared by DCM Building Design, dated 31.10.2024, drawing
number DD-1.01, issue C (Amended in red by SARA).
(b) and (c)
(b) Provide road access works comprising a minimum 6 metres wide
vehicle crossing - heavy duty driveway, at the road access Prior to the
location referred to in part (a) of this condition, generally in commencement of use
accordance with Site Plan, prepared by DCM Building Design, and to be maintained at
dated 31.10.2024, drawing number DD-1.01, issue C (Amended all time.
in red by SARA).
(c) Design and construct the road access works, referred to in part
State Assessment and Referral Agency Page 4 of 10