Engineering Operational Works Plans
Attached to the e-mail Application for operational works - 108 Black Mountain Range Road Black Mountain.
Original PDF page 4, section 1. The text section number identifies this passage in the reader.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn EROSION & SEDIMENT CONTROL
INSTALLATION SEQUENCING
EROSION AND SEDIMENT CONTROL SEQUENCING
INSTALLATION OF ENTRY / EXIT DAY 1 ALL NOMINATED WORKS ARE TO BE STAGED SO THAT DISTURBED AREAS ARE KEPT TO A MINIMUM. EROSION AND SEDIMENT CONTROL MEASURES
SHALL BE IMPLEMENTED IN ACCORDANCE WITH THE FOLLOWING SEQUENCE.
INSTALLATION OF PERIMETER SEDIMENT FENCES DAY 1 · PROVIDE A STABILISED SITE ACCESS, INCLUDING SHAKE DOWN DEVICE AT THE CONSTRUCTION SITE ENTRANCE INCLUDING SILT FENCES AS
REQUIRED.
EXCAVATION OF SEDIMENT BASINS INCLUDING PRIOR TO STRIPPING
· ESTABLISH 'CLEAN WATER DIVERSION' OF UPSTREAM WATER AROUND PROPOSED DISTURBED AREAS AND STOCKPILES. THE CLEAN WATER
INSTALLATION OF ENTRY CHUTES AND OF TOPSOIL AND DIVERSION DRAINS TO BE STABILISED AS SPECIFIED.
OVERFLOW STABILISATION BULK EARTHWORKS
· 'NO-GO' (RESTRICTED ACCESS) ZONES ARE TO BE ESTABLISHED. LAND OUTSIDE THE ESSENTIAL WORKS AREAS SHOULD REMAIN UNDISTURBED
AND IN ITS NATURAL CONDITION
INSTALL CUT-OFF DRAINS AND CHECK DAMS AS PRIOR TO STRIPPING
· SEDIMENT BASINS AND SEDIMENT TRAPS ARE TO BE CONSTRUCTED WITH APPROPRIATELY STABILISED DIVERSION STRUCTURES AND
IDENTIFIED. OF TOPSOIL AND EMERGENCY SPILLWAYS.
BULK EARTHWORKS
· INSTALL SEDIMENT FENCES DOWNSTREAM OF ALL WORKS AREAS.
· STRIP TOPSOIL AND STOCKPILED FOR LATER USE ONSITE INCLUDING SILT FENCES DOWNSTREAM OF ALL TOPSOIL STOCKPILES.
HOLD POINT SUPERVISING ENGINEER
· STABILISE ALL BATTER / EMBANKMENTS INCLUDING SILT FENCES AT THE TOE OF BATTERS.
TO SIGN OFF
· ALL DISTURBED AREAS ARE TO BE PROGRESSIVELY STABILISED USING HYDROSEEDING.
INSTALLATION OF EROSION AND SEDIMENT CONTROL · INSTALL INLET TRAPS UPON COMPLETION OF DRAINAGE AND ROADWAORKS.
MEASURES SUCH AS INLET PROTECTION, CHECK · LAY TURF STRIPS ALONG CONCRETE FOOTPATHS AND BACK OF KERBS.
DAMS, WINDROWS ETC AS IDENTIFIED ON THE ESC · FINAL SITE LANDSCAPING IS TO BE CONDUCTED AS SOON AS POSSIBLE AFTER CONSTRUCTION COMPLETION.
DRAWINGS AND AS DIRECTED ON SITE BY THE · ALL EROSION AND SEDIMENT CONTROL MEASURES SHALL BE INSPECTED AND MAINTAINED AS SPECIFIED.
SUPERVISING ENGINEER.
NOTE: EROSION AND SEDIMENT CONTROL MEASURES ARE TO REMAIN IN
PLACE AND MAINTAINED UNTIL 80% OF GROUNDCOVER IS ACHIEVED NOTE:
OR AS DIRECTED BY THE SUPERVISING ENGINEER. THESE EROSION AND SEDIMENT CONTROL PLANS TO
BE READ IN CONJUNCTION WITH "BEST PRACTICE
NOTE: EROSION AND SEDIMENT CONTROL MANUAL 2008."
1. REFER TO DWG No. #### FOR EROSION & SEDIMENT CONTROL DETAILS. SITE INSPECTION FORMS & ITP'S FORM PART OF THIS
EROSION AND SEDIMENT CONTROL PLAN
EROSION & SEDIMENT CONTROL NOTES
1. ALL EROSION & SEDIMENT CONTROL DEVICES ARE TO BE INSTALLED IN ACCORDANCE WITH THESE EROSION AND SEDIMENT CONTROL PLANS SHALL BE READ IN CONJUNCTION WITH:
THE I E AUST SOIL EROSION & SEDIMENT CONTROL MANUAL, AS DETAILED ON THIS PLAN, OR "BEST PRACTICE EROSION AND SEDIMENT CONTROL MANUAL - 2008"
AS REQUIRED FOR COMPLIANCE WITH THE REQUIREMENTS OF THE ENVIRONMENTAL "BCC SEDIMENT BASIN DESIGN CONSTRUCTION AND MAINTENANCE GUIDELINES"
MANAGEMENT PLAN. "IECA BEST PRACTICE DESIGN GUIDELINES" NOTABLY APPENDIX B, D, I & J
2. THE CONTRACTOR IS RESPONSIBLE FOR ENSURING SEDIMENT & EROSION CONTROL
DEVICES ARE INSPECTED & MAINTAINED AS FOLLOWS:
(A) DURING CONSTRUCTION
(i) DAILY DURING DRY WEATHER
SEDIMENT CONTROL DEVICE CONSTRUCTION, MAINTENANCE AND
(ii) PRIOR TO PREDICTED STORM EVENTS
REMOVAL IS TO BE IN ACCORDANCE WITH:
(iii) TWICE DAILY DURING PROLONGED RAIN
· "BEST PRACTICE EROSION AND SEDIMENT CONTROL MANUAL - 2008"
(iv) DURING AND AFTER MAJOR STORM EVENTS
· "BCC SEDIMENT BASIN DESIGN CONSTRUCTION AND MAINTENANCE
(B) DURING DEFECTS LIABILITY PERIOD
GUIDELINES"
(i) WEEKLY DURING DRY WEATHER
· BEST PRACTICE EROSION AND SEDIMENT CONTROL BOOK 6 -
(ii) PRIOR TO PREDICTED STORM EVENTS
STANDARD DRAWINGS IS TO BE REFERRED TO DURING
(iii) TWICE WEEKLY DURING PROLONGED RAIN
CONSTRUCTION.
(iv) DURING AND AFTER MAJOR STORM EVENTS
3. THE CONTRACTOR IS TO CONSTRUCT AN ENTRY/EXIT SEDIMENT TRAP AS DETAILED PRIOR
TO THE COMMENCEMENT OF ANY EARTHWORKS.
4. ALL STOCKPILES TO BE TEMPORARILY GRASSED & GRADED TO ENSURE CONTROL OF
RUNOFF. ALTERNATIVELY, SEDIMENT FENCES TO THE DOWNSTREAM FACE OF STOCKPILES
ARE TO BE INSTALLED, WITH CUT-OFF DRAINS UPSTREAM.
5. ROUGHEN ALL SURFACES PRIOR TO TOPSOIL PLACEMENT. ROUGHENING TO CONSIST OF
LATERAL (90° TO SLOPE) GROOVES 100mm DEEP AT 2m MAX. SPACINGS.
6. ALL EXPOSED SURFACES, ONCE COMPLETED SHALL BE IMMEDIATELY STABILISED TO
PREVENT EROSION. ROUGHEN SURFACE BY FORMING LATERAL GROOVES 50mm DEEP AT 1m
MAX. SPACINGS AND 5m MAX. LENGTHS.
7. SEDIMENT & EROSION CONTROL DEVICES (OTHER THAN THOSE ALREADY SHOWN) TO BE
INSTALLED WHERE NECESSARY & AS DIRECTED ON SITE BY THE SUPERINTENDENT.
8. SEDIMENT & EROSION CONTROL DEVICES ON THIS PLAN ARE INDICATIVE ONLY. IT IS THE
RESPONSIBILITY OF THE SITE MANAGER TO ENSURE THAT THE INTENT OF THIS PLAN AND
THE ENVIRONMENTAL MANAGEMENT PLAN ARE COMPLIED WITH.
9. EROSION AND SEDIMENT CONTROL DEVICES/STRATEGIES TO BE COMPLETED PRIOR TO
DISTURBANCE OF THE SITE, AND SHALL REMAIN IN PLACE UNTIL PERMANENT WORKS ARE
COMPLETE AND CATCHMENT VEGETATION IS ESTABLISHED (75% GRASS COVER MINIMUM) .
10. AREAS OF WORKS THAT REQUIRE DISTURBANCE OF SOIL SHALL BE KEPT TO A MINIMUM TO
LIMIT THE EXPOSURE OF SOIL TO RAIN-DROP IMPACT AND OTHER FORMS OF
WIND/STORMWATER EROSION.
11. ALL WORK IS TO BE COMPLETED IN ACCORDANCE WITH ALTA PROJECTS STANDARD
SPECIFICATION.
NOTE: ONLY DRAWINGS MARKED "FOR CONSTRUCTION" AND BEARING AN ORIGINAL SIGNATURE SHALL BE USED FOR CONSTRUCTION Design:
PURPOSES.
SWT PROJECT: DRAWING TITLE:
ALTA PROJECTS
Drawn: SWT
A.B.N. 611355330 EROSION AND SEDIEMNT CONTROL NOTES
FOR APPROVAL Date: July 2020 26 Memorial Avenue, Cotton Tree PROPOSED SUBDIVISION ESTATE
NOT FOR CONSTRUCTION PO Box 559, Cotton Tree, QLD, 4558 Revision Sheet
Checked:. . . . . . . . . . .
Tel (07) 5475 4125 Fax (07) 5479 1607
Email: [email protected]
at 108 BLACK MOUNTAIN RANGE ROAD, BLACK MOUNTAIN
DRAWING No:
A6578/20/ES02 B 2 of 3
STEPHEN ROBERTS
B
A
31/08/2021
16/08/2021
ISSUE FOR APPROVAL
ISSUE FOR APPROVAL
S.T.
S.T.
S.R.
S.R.
.......................
DIRECTOR APPROVAL Datum AHD
Web: http://www.alta.net.au for TOTAL CONCEPT HOMES
REV DATE DESCRIPTION BY CHKD RPEQ - 7665 A1 SHEET SIZE FILENAME : A6578 - ES02 EROSION AND SEDIEMNT CONTROL NOTES.dwg - DATE : 31/8/21 - 2:15pm - XREF's: H-Approved-SR; H-Checked-SR Council Ref: ............
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.