4.0      TRAFFIC OPERATIONS

4.1      DEVELOPMENT PROFILE

         4.1.1        Staging
         For the purpose of quantifying the traffic impact of the proposed development, the following
         development staging has been adopted:

         —        Traffic Counts:                              2026
         —        Development Application:                     2028
         —        Construction and Occupation:                 2028
         —        10-Year Design Horizon:                      2038

         4.1.2        Assessment Scenarios
         This has led to the following assessment scenarios being considered:

         —        opening year (2028) pre-development
         —        opening year (2028) post-development
         —        future year (2038) pre-development
         —        future year (2038) post-development

         4.1.3        Background Traffic Growth
         The background traffic growth for the impact assessment area has been estimated based on the
         10-year growth in Average Annual Daily Traffic (AADT) as reported by TMR for Eumundi Noosa
         Road (identification number 20363). A simple growth has been used, as required by Section 4
         of TMR’s GTIA. This calculation is summarised in Table 4.1.

         Table 4.1:            BACKGROUND TRAFFIC GROWTH
           SITE                                         2014 VPD               2024 VPD                  % INCREASE

           20363 Eumundi Noosa Road                       11,700                 13,920            19.0% over last 10 years
           Forecast (= 12 / 10 x 19.0%)                                                            25.3% over next 12 years

         Accordingly, background traffic between 2026 (the year of the counts) and 2038 (year of opening
         plus ten years) is expected to grow by 25.3%.

4.2      TRAFFIC GENERATION
         The traffic generation for the site has been determined as follows:

         —        weighbridge data was used to determine a trip generation rate for:

                  —       green waste:                         1.47 vehicles per tonne
                  —       mulch / compost sales:               0.21 vehicles per tonne

         —        of the 30,000 tonnes of green waste expected post development, approximately 5,220
                  tonnes would be received in an equivalent month to the weighbridge data (ie 17.4%)
         —        once processed, this would result in approximately 3,130 tonnes of compost (ie 60% of
                  green waste mass)



 P:\2025-26\26-369 NOOSA RESOURCE RECOVERY CENTRE\OUTPUTS\26-369 TRAFFIC IMPACT ASSESSMENT FINAL.DOCX                    14

Used in these records

About this file

File size
9.3 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 5 - Traffic Impact Assessment Final PTT.pdf · 9.3 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.