Attachment 5 - Traffic Impact Assessment Final PTT · 132005.638.06
3.1.3 Transfer station design capacity
To determine the number of bays required data provided by NSC for November 2023 weighbridge passes
have been analysed to evaluate various arrangements and the associated level of service, and queuing from
transfer. Clearing time for each bay type, including vehicle manoeuvring and unloading after weighbridge
access, has been taken as the limiting design factor in selecting the number transfer station bays required.
There is approximately 40m of available queue length from the entry roundabout to the weighbridge at
transfer areas. The estimated time to manoeuvre in, unload and manoeuvre out, with sorting by patrons at
transfer bays for each vehicle type is provided in Appendix A. Sensitivity of total time required, wait time and
queue length by number of bays is provided in Appendix B and has been used to select the number of each
bay type, where queue length does not extend into the roundabout area at site entry. Vehicle volume
estimated average unload time and frequency are provided in Table 12.
Bay lengths are assigned for small vehicles, vehicles towing trailers, and large vehicles. Each of the three
categories have differing manoeuvring and length requirements. Large vehicles can be assigned to transfer
station bays or diverted to open tipping floor (preferred). This separation of bays also addresses the issue
identified with trailer manoeuvring difficulty; particularly public vehicles raised by the NSC operational team.
Table 12 Transfer bays and utilisation, minimum number of bays required
Bay category Vehicle types Number of Weighted average Maximum Minimum
vehicles unload time vehicles per bays
hour observed required
Small A - car 3423 11.06 minutes 22 4
vehicles E - van or ute + 1 minute 4 occasions,
J - light commercial vehicle manoeuvring into November
bay and entering/ 2023
H - rigid truck exiting
Vehicles B – cars towing trailers 1338 12.79 minutes 12, occurs 3
towing trailers F – vans and utes towing + 2 minutes once.
trailers manoeuvring into Saturday,
bay and entering/ 18 November
exiting 2023
Large K - compactor truck 84 26.37 minutes 3, occurs once. Bulk
vehicles G - rigid truck towing a trailer + 2 minutes Friday, Tipping
manoeuvring, bulk 17 November Floor
L - articulated motor vehicle
tipping floor is a loop 2023
M - vehicle carrying containers access road but
N - vehicle carrying requires positioning
containers (Deeming) of vehicle.
Sensitivity on number of bays has been determined for vehicle volumes up to 20% exceeding the volumes
observed in the November 2023 data to understand the impact of traffic volume variations. Peak periods of
high volume can be managed through reduced public sorting (reducing time in transfer bays) and deferred
operator sorting to mitigate traffic queuing. However, increasing the number of bays to five small bays, four
trailer bays and a bulk tipping floor for large vehicles provides additional risk management, queue length and
level of service (wait time) benefits that outweigh the loss of operational space and have been incorporated
into the Masterplan Design. These impacts are provided in tables in Appendix D to Appendix F. In
considering cumulative queuing between bay types, the vehicles to bulk tipping floor (BTF) are not included
as there is opportunity for vehicle staging within the warehouse, small and trailer bays are captured in
Table 13 to Table 16.
The minimum number of bays that will accommodate the anticipated traffic volumes without exceeding 40m
of queue length is four small bays and four trailer bays from the sensitivity cases. At 120% sensitivity, this is
1m from reaching the maximum queue length available and provides no opportunity for operational activities
or delays within the bays. Five small bays, four trailer bays and a bulk tipping floor arrangement can
accommodate the 120% sensitivity case of vehicle volumes within the available queuing length of 40m in the
Masterplan design, this was selected for implementation in the masterplan design. There is capacity in this
arrangement to accommodate operations including change of full skips, bays not in use due to full skips,
long duration unloading by the public, or interactions with operators.
Project number 526384 File Noosa Masterplanning Report 2025-02-07 Revision 0 19
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 5 - Traffic Impact Assessment Final PTT.pdfRelated documentApplication case desk ↗
About this file
- File size
- 9.3 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.