Appendix B - Amended Biome Consulting Response
Attached to the e-mail Amended Biome Report - stormwater in addition to Information Response - MCU170551 - 20 Trading Post Road Cooroy.msg.
The original of this document is very large (16.0 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Table 3-8: Central Basin Stage Storage Discharge Relationship
Accumulated
Stage (m AHD) Discharge (m3/s) Basin Control/ Structure
Storage (m3)
99.6 0 0.00 Primary Front & Side Orifices
99.7 240 0.06
99.8 491 0.17
99.9 751 0.33
100.0 1,021 0.53
100.1 1,301 0.77
100.2 1,591 0.87
100.3 1,891 0.96
100.4 2,202 1.04 Primary Outlet Pit Weir Level (RL100.45mAHD)
100.5 2,523 1.21
100.6 2,944 1.66
100.7 3,379 2.01
100.8 3,828 2.06
100.9 4,291 2.12 Major Overflow Weir (Major & Extreme Events)
101.0 4,774 2.83
101.1 5,272 4.15
101.2 5,783 5.95
101.3 6,308 8.16 Minimum Top of Embankment (RL 101.3m AHD)
Since the Issue A report, stage-storage-discharge relationship for the Central Basin has been updated and
remodelled. The outlet configuration has not been changed as it is still appropriate and therefore has not been
modified, however, a slight modification to the width of the overflow weir has changed discharge values.
3.2.6 DEVELOPED MITIGATED PEAKS FLOW RESULTS
Modelling was undertaken for the all recurrence interval storm events up to and including the 1% AEP storm event with
storm durations ranging from 30 to 120 minutes (these were considered the critical durations). A comparison between
peak flows for the existing and developed mitigated scenarios has been provided at each discharge location in Table 3-9
below.
Table 3-9: Developed Mitigated Scenario Peak Flow Comparison
Existing Peak Developed Peak Percentage
AEP Discharge (m3/s) Discharge (m3/s) Difference
Discharge Location A (North)
63% 0.17 0.16 -5%
39% 0.26 0.23 -8%
18% 0.36 0.34 -4%
10% 0.43 0.41 -4%
5% 0.55 0.46 -17%
2% 0.66 0.59 -12%
1% 0.77 0.77 0%
AEP Discharge Location B (Central)
63% 1.14 1.12 -2%
39% 1.71 1.54 -10%
18% 2.54 2.30 -9%
10% 3.02 2.73 -10%
5% 3.69 3.55 -4%
2% 4.28 4.09 -4%
1% 4.95 4.62 -7%
16-001014-01B | STORMWATER MANAGEMENT PLAN COOROY RETIREMENT COMMUNITY, TRADING POST
(SWMP) | PALM LAKE RESORTS ROAD, COOROY | 12
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.