Attachment D - Planning Scheme Statement
Attachment C
Assessment Against the Planning Scheme – Earthworks Code
Performance Outcomes Acceptable Outcomes Compliance
Effects of works
Drainage AO1
PO1 Can comply – proposal plans have been
Finished surface levels ensure land Filled or excavated areas have a minimum gradient prepared by SCG Consulting Engineers to
is free draining. of 0.5% and drain to Council’s stormwater demonstrate the ability to comply to PO1 and
infrastructure where available, or where stormwater are included in Attachment B.
infrastructure is not available, toward the street.
Hydraulics No acceptable outcome provided Can comply – proposal plans have been
PO2 prepared by SCG Consulting Engineers to
Change to the levels on site do not demonstrate the ability to comply to PO2 and
have an adverse impact on the are included in Attachment B.
flooding and drainage .
characteristics off-site.
Geotechnical considerations AO3.1
PO3 Filling works are undertaken in accordance with Can comply – proposal plans have been
Earthworks do not result in Council’s Planning Scheme Policy PSP6 prepared by SCG Consulting Engineers to
geotechnical instability on-site or Engineering design standards - roads, drainage demonstrate the ability to comply to PO3 and
to nearby premises. and earthworks. are included in Attachment B.
AO3.2
Where the filling is for residential, commercial or
industrial purposes the works comply with
Australian Standard - Guidelines for earthworks on
commercial & residential development.
Local amenity AO4.1
PO4 The following control measures are implemented— Can comply – proposal plans have been
Undertaking earthworks does not prepared by SCG Consulting Engineers to
adversely impact on the amenity of a) regular water spraying of exposed areas to demonstrate the ability to comply to PO4 and
the local area by way of dust, noise or suppress dust; are included in Attachment B.
visual amenity. b) provision of dust stabilised or sealed internal
roads;
c) protective covering of exposed areas that are left
for more than 2 weeks; and
d) unless a development permit provides otherwise,
disturbed areas are revegetated using species
identified in Council's Planning Scheme
Policy PSP2 Landscaping.
AO4.2
Earthworks are undertaken only during the hours
of 7:00am to 6:00pm, Monday to Friday and
7:00am to 3:00pm on Saturday. No work is
undertaken on Sunday or public holidays.
Vegetative waste AO5.1
PO5 Cleared vegetation is transported off-site for Can comply – Any cleared vegetation will be
Vegetation cleared from a disposal in an approved green waste disposal disposed of appropriately.
development site is disposed of in facility.
an environmentally responsible
manner. AO5.2
Cleared vegetation is mulched on-site and reused
for landscaping of the finished development.
AO5.3
Cleared vegetation is disposed of for the purpose of
firewood.
AO5.4
Disposal of vegetative waste by burning off is
avoided.
Managing contamination risk AO6.1
PO6 Fill material is solid clean earth, free of putrescible Complies - Fill material will come from cutting
Materials used as fill are suitable or refuse material, vegetation, acid sulfate at the site.
for development and future use of soils, building or construction material or other
the land and filling or excavation material or contaminants.
works do not result in the
contamination of land. AO6.2