29. All stormwater drainage (including roof water overflow from the rainwater storage system)
shall be collected and discharged so there is no net increase in stormwater runoff or intensity
from the site. Stormwater drainage permitted to drain from the site shall be discharged into a
detention and infiltration system designed and certified by a suitably qualified Registered
Professional Civil Engineer or/and be discharged to the kerb & channel street drainage system
in Elanda Street. Development Permit for Operational Works is required.
The maximum discharge of stormwater drainage allowable to Council’s kerb & channel street
drainage system at any one location is 25 litres/second.
30. Any stormwater detention and/or infiltration systems shall not obstruct maintenance access to
any sewer main on the site and shall be located away from the zone of influence of Council’s
sewer system.
A detailed maintenance plan shall be prepared for any proposed stormwater detention and
filtration systems, which shall be submitted to the Council for approval prior to obtaining a
Development Permit for Operational Works.
The approved maintenance plan shall be incorporated in the Community Management
Scheme for the development and a copy of this shall be provided for Council’s records prior to
commencement of the approved Use.
A Development Permit for Building Works shall not be granted until a Development Permit for
Operational Works has been issued in regard to the drainage scheme.
31. To ensure that polluted run-off does not enter Council’s stormwater drainage system,
stormwater run-off from the carparking areas and the driveways shall have the first flush (the
first 12 mm of rainfall or hose-down) collected in a grease/oil arrestor/gross pollutant trap
provided on site prior to being permitted to discharge into stormwater detention system.
All other clean stormwater, such as roof water and overflows from stormwater tanks, can be
collected on site and discharged through a single underground drain line directly into the
proposed drainage disposal system, bypassing the grease/oil arrestor/gross pollutant trap.
To this end, a detailed maintenance plan shall be prepared for the proposed grease/oil
arrestors/gross pollutant trap, which shall be submitted to the Council for approval prior to
obtaining a Development Permit for Operational Works.
The approved maintenance plan shall be incorporated in the Community Management
Scheme for the development and a copy of this shall be provided for Council’s records prior to
commencement of the approved Use.
A Development Permit for Building Works shall not be granted until a Development Permit for
Operational Works has been issued in regard to the drainage scheme.
32. All site stormwater drainage shall be by means of a gravity system.
Sewer Mains
33. The site shall be connected to Council’s existing sewerage reticulation systems and be
constructed in accordance with Council’s standards and requirements at no cost to Council.
34. Given that the existing lots are to be amalgamated, the existing sewer main along the rear of
the site shall be shortened to 1.5 metres north of the existing sewer manhole at the north east
corner of the site.
35. The ‘zone of influence’ (taken as the area within a 45-degree angle measured from the invert
of the sewer main to the finished surface level) of the retained sewer main and manhole shall
be accurately located and determined by a licensed Surveyor and shown on all plans
submitted for Operational Works approval.
Page 5 of 15
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED Decision Notice - 010.2007.00002174.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 84 KB (small file)
- File type
No other editions are linked here.