Council archive · source document
REFERENCED DOCUMENT Assessment of Existing Wastewater Infrastructure - MCU13/0064
Table 3: Minimum Required Irrigation Area
Irrigation Area as Determined by Table M1
AS1547:2000 Soil Category
of AS 1547
Soil Category 2 – Sand 552m2
From Table M1 of AS1547:2012 assuming a hydraulic loading of 2,760 litres per
day and a Category 2 soil (DIR of 5mm/day), a minimum application area of
552m2 is required.
Suitability of Existing Wastewater Treatment System and Land Application Area
Based on information supplied by the service agent (H2Gold) the existing
Novaclear AWTS has the capacity to handle a peak hydraulic loading of
2,700L/day. However, based on the relevant guidelines a peak hydraulic loading
of 2,760L/day (14EP) was calculated. Therefore, through the modification of the
Novaclear AWTS pump timing, the peak design capacity of the system is to be
expanded to handling 2,760L/day (14EP).
The accommodation facility is currently serviced by a land application area of
540m2, based on a daily irrigation rate of 2,700L (peak load). However, based on
the calculated hydraulic loading of 2,760L/day a minimum land application area
of 552m2 is required. Therefore, it is proposed to limit the daily irrigation rate to
2,700L through the modification of the irrigation pump system. The additional
60L/day generated during peak occupancy will be retained within the 10,000L
wet weather storage tank for irrigation during off peak times.
The nature of the facility would normally result in fluctuating wastewater flows,
as it is anticipated that it will not operate at 100% occupancy at all times. Given
that the facility has sufficient capacity to treat, manage, irrigate and if necessary
retain effluent at times when required, the impact can be appropriately
accommodated.
The existing Novaclear AWTS and subsurface land application area appear to be
in sound operating condition to accommodate the proposal.
Provided the on-site sewerage facility is maintained in accordance with the
recommendations provided in the Site and Soil Evaluation Report (ref no. 2771-
02) and operation and maintenance manual, there will be minimal risk of impact
to the site and surrounding areas. The system must be operated and maintained in
compliance with the manufacturer’s requirements to ensure this risk is
appropriately managed.
p: 07 5450 2688 e: [email protected] PO Box 1250, Buddina Q 4575
f: 07 5450 2686 www.future-plus.com.au ABN 23 658 506 336
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
REFERENCED DOCUMENT Assessment of Existing Wastewater Infrastructure - MCU13/0064Related documentApplication case desk ↗
About this file
- File size
- 1.1 MB (small file)
- File type
No other editions are linked here.