Engineering Report & Stormwater Management Plan
Date: 16/06/2014 Document No.: 14012-ENG-01.Docx
By: AvT Revision No.: B
The SPEL Puraceptor P.040.C1.2C has a spill containment capacity of 9000l which is sufficient
to hold the contents of a fuel tanker in case of an emergency spill.
Refer to Appendix F for the SPEL Puraceptor Operations and Maintenance Manual.
Car Wash Treatment
It is anticipated that the water supply for the proposed car wash will be obtained from a
combination of council water, captured roofwater and water reuse. The car wash treatment
and water reuse for this proposed development will be by others during the detailed design
phase of the project and will be subject to plumbing approval.
f. Stormwater Quantity Management
Noosa Regional Council Policy requires that a development ensure Non Worsening of
stormwater flows up to and including Q100 stormwater events. The proposed development
includes detention basin storage in the South East corner of the site. With this detention
basin, it is considered that the proposed development will not cause any worsening of flows
from the site.
The new proposed multi-use development will have a larger impervious area than the existing
undeveloped site and will require a stormwater detention system to mitigate the effects of
the additional runoff. Detailed calculations of the detention required are included in Appendix
G of this report and are summarised in the table below:
Runoff Coefficient (C10) - Undeveloped: 0.65 tc = 6 min.
Runoff Coefficient (C10) - Developed: 0.85 tc = 6 min.
PARAMETERS
ARI 2yr 5yr 10yr 20yr 50yr 100yr
Rainfall Intensity mm/hr 150.0 184.0 204.0 232.0 268.0 296.0
Frequency Factor fy= 0.85 0.95 1.00 1.05 1.15 1.20
Undeveloped C Cu= 0.60 0.67 0.70 0.74 0.81 0.84
Developed C Cd= 0.70 0.78 0.82 0.86 0.94 0.98
FLOWS
Undeveloped Flow Qu= C*I*A l/s 1248 1711 1997 2385 3018 3478
Developed Flow Qd=Qi= C*I*A l/s 1462 2005 2340 2794 3535 4074
Difference l/s 214 293 342 409 517 596
Outlet Flow Qo = l/s 1248 1711 1997 2385 3018 3478
Table 5.10: Quantity Summary
A PO Box 26, Carina Q 4152 16 | P a g e
E [email protected]
W www.vtce.com.au
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.