MCU14/0056 - Attachment G - Engineering Report & Stormwater Management Plan

of 103

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
                                                                                                                              ENG
                                                            Engineering Report & Stormwater Management Plan
                                                    Date:          16/06/2014        Document No.:        14012-ENG-01.Docx

                                                     By:              AvT            Revision No.:                B


  Based on the calculated peak flows, the detention volume required for proposed multi-use
  development is shown in the table below.


                                                   INITIAL VOLUME
Reduction
                   r=             (Qi-Qo)/Qi
   ratio                                                           0.146 0.146 0.146            0.146      0.146 0.146
  Inflow
                   Vi=             4tc*Qi/3                l/s
 Volume                                                             702     962        1123     1341       1697       1956
                                                               3
                  Culp         Vs=(r(1+2r)/3)*Vi           m         44         61      71           85     107       123
                                                               3
Volume to         Boyd             Vs=r*V=                 m        103     141         164      196        248       286
 Retain          Carroll Vs=(r(3+5r)/8)*Vi                 m   3
                                                                     48         66      77           92     116       133
                                                               3
                 Basha         Vs=(r(2+r)/3)*Vi            m         73     101         118      140        178       205
                                                               3
             Average Volume to Retain =                    m        67       92        107       128       162        187
        Table 5.11:            Detention Summary

  Based on these calculations it was determined that a detention storage volume of 187m3 is
  required to ensure that the developed flow is equal to or less than the undeveloped flow.

  It is proposed that all runoff from the impervious areas are to be drained to the detention
  basin. The detention basin will be owned and maintained by the property owner.

                         g. Maintenance

      Construction Phase Management Plan
  Potential construction phase impacts include the following:
  • Sedimentation and erosion
  • Management of contaminated soils and materials on the site Construction Material (such
      as cement)

       General
  The objective of the Construction Phase Management Plan is to comply with the requirements
  of the Queensland Environmental Protection Act 1994 and Environmental Protection (Water)
  Policy 2009 so that the environmental values of effected receiving waters are maintained or
  enhanced. In essence the purpose of the Plan is to prevent polluted stormwater being
  discharged to the local waterways.

      Performance Indicators
  The management is not being effective when any of the following occur during the
  construction phase of the project.
  • The required water quality objectives are not achieved,
  • Contaminated water is released off site.



  A PO Box 26, Carina Q 4152                                                                                 17 | P a g e
  E [email protected]
  W www.vtce.com.au
Log in to download the original file

MCU14_0056 - Attachment G - Engineering Report & Stormwater Management Plan.pdf · 9.8 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.