MCU14/0056 - Attachment G - Engineering Report & Stormwater Management Plan
Plans and drawings
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn ENG
Engineering Report & Stormwater Management Plan
Date: 16/06/2014 Document No.: 14012-ENG-01.Docx
By: AvT Revision No.: B
Based on the calculated peak flows, the detention volume required for proposed multi-use
development is shown in the table below.
INITIAL VOLUME
Reduction
r= (Qi-Qo)/Qi
ratio 0.146 0.146 0.146 0.146 0.146 0.146
Inflow
Vi= 4tc*Qi/3 l/s
Volume 702 962 1123 1341 1697 1956
3
Culp Vs=(r(1+2r)/3)*Vi m 44 61 71 85 107 123
3
Volume to Boyd Vs=r*V= m 103 141 164 196 248 286
Retain Carroll Vs=(r(3+5r)/8)*Vi m 3
48 66 77 92 116 133
3
Basha Vs=(r(2+r)/3)*Vi m 73 101 118 140 178 205
3
Average Volume to Retain = m 67 92 107 128 162 187
Table 5.11: Detention Summary
Based on these calculations it was determined that a detention storage volume of 187m3 is
required to ensure that the developed flow is equal to or less than the undeveloped flow.
It is proposed that all runoff from the impervious areas are to be drained to the detention
basin. The detention basin will be owned and maintained by the property owner.
g. Maintenance
Construction Phase Management Plan
Potential construction phase impacts include the following:
• Sedimentation and erosion
• Management of contaminated soils and materials on the site Construction Material (such
as cement)
General
The objective of the Construction Phase Management Plan is to comply with the requirements
of the Queensland Environmental Protection Act 1994 and Environmental Protection (Water)
Policy 2009 so that the environmental values of effected receiving waters are maintained or
enhanced. In essence the purpose of the Plan is to prevent polluted stormwater being
discharged to the local waterways.
Performance Indicators
The management is not being effective when any of the following occur during the
construction phase of the project.
• The required water quality objectives are not achieved,
• Contaminated water is released off site.
A PO Box 26, Carina Q 4152 17 | P a g e
E [email protected]
W www.vtce.com.au
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.