MCU14/0056 - Attachment G - Engineering Report & Stormwater Management Plan
Plans and drawings
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn Corner Myall Street & Ferrells Road Cooroy, QLD 4563
State development assessment provisions
Module 18 — State transport infrastructure protection Response column key:
Achieved
P/S Performance solution
Stormwater and drainage impacts on state transport infrastructure state code NA Not Applicable
N/A Not applicable
Performance outcomes Acceptable outcomes Response Comment
Stormwater and drainage management
PO1 Stormwater management for
the development must ensure there
AO1.1 The development does not result in
stormwater or drainage impacts or actionable
The proposed development is downstream
of the state controlled Bruce Highway and
is no worsening of, and no nuisance within an existing or future state therefore it is anticipated that the
actionable nuisance in relation to transport corridor. proposed developments will not impact on
peak discharges, flood levels, Editor’s note: It is recommended that basic the state controlled transport corridor.
frequency or duration of flooding, stormwater information is to be prepared to
flow velocities, water quality, demonstrate compliance with AO1.1. OR The proposed development also achieves a
sedimentation and scour effects on
non-worsening impact by providing a
an existing or future state transport AO1.2 A stormwater management statement stormwater detention basin to mitigate
corridor for all flood and stormwater certified by an RPEQ demonstrates that the flows.
events that exist prior to development will achieve a no worsening impact or
development, and up to a 1 per cent actionable nuisance on an existing or future state
annual exceedance probability. transport corridor. OR
A01.3 A stormwater management plan certified by
an RPEQ demonstrates that the development will
achieve a no worsening impact or actionable
nuisance on a state-controlled road. OR
AO1.4 For development on premises within 25
metres of a railway, a stormwater management
plan certified by an RPEQ demonstrates that:
(1) the development will achieve a no worsening
impact or actionable nuisance on the railway
(2) the development does not cause stormwater,
roofwater, ponding, floodwater or any other
drainage to be directed to, increased or
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.