61. Any connection required to Council’s water mains shall only be undertaken by
Council.
Sewerage Reticulation
62. Each lot shall be connected to Council’s Sewerage reticulation systems in accordance
with the Water and Sewerage Design Guidelines and Council requirements, at no cost
to Council. Sewerage Infrastructure shall be provided to the development generally in
accordance with the Carpenters Road, Cooroy Water Supply & Sewerage Analysis,
March 2007, as prepared by John Wilson & Partners (JWP).
63. The sewer pump design shall be based on a development density of 30 ET/ha with a
single pump duty of 7 litres per second with a 100mm rising main.
64. Where sewers are required to cross any creeks the sewer main shall be designed to
withstand debris loading during a 1 in 100 year flood event.
65. All connections to the sewer system shall be carried out either by Council or by a
Council approved Contractor and at no cost to Council.
General Water and Sewerage Requirements
66. All water supply and sewerage works (including any necessary improvements to the
existing services and/or the creation of any easements) required in order to service
the proposed development shall be provided at no cost to Council.
67. Detailed design drawings and calculations shall be submitted with an application for a
Development Permit for Operation Works in respect of water or sewer works. To
avoid conflict with other underground pipes or services, all existing and proposed
services required by the development shall be shown on the plans.
68. All Water Supply and Sewerage Reticulation designs shall be prepared in consultation
with Council’s Water and Sewerage Capital Works Manager (Phone 07 5449 5288).
Power Supply
69. An underground electricity service shall be provided to each proposed lot.
To this extent, an approved ENERGEX Electrical Design Consultant shall work in
conjunction with Council’s Manager - Works Support to prepare detailed designs of
the electrical proposal.
The detailed designs shall then be submitted to ENERGEX for approval and a copy of
their approval submitted to Council in conjunction with a “Certificate of Electricity
Supply for Proposed Subdivisions” (prepared by an approved ENERGEX electrical
design consultant) prior to Council endorsing the Plan of Survey.
Any agreement with ENERGEX or an approved ENERGEX electrical design
consultant shall be wholly at the applicant’s expense and shall not entail a financial
encumbrance on future purchasers of the proposed lots.
Street lighting and pathway lighting shall have a high energy efficient rating and shall
generally be provided in accordance with the principles of Council’s Engineering
Design Standards. The lighting shall be suitably hooded/screened to ensure that
adjoining properties are not adversely affected by spill light.
Telecommunications
70. The requirements for telecommunication services shall be satisfied in relation to the
provision of new telephone services to the proposed lots. In this regard written
confirmation from an approved telecommunication agency shall be submitted to the
Council prior to Council endorsing the Plan of Survey.