External Works
13. The frontages of the subject site to Lake Macdonald Drive and Dianella Court and the
intersection of Lake Macdonald Drive and Dianella Court must be upgraded. The works must
be undertaken in accordance with an Operational Works approval and must be generally in
accordance with drawings numbered 233467 - C003 – Revision C, 233467 – C010 –
Revision C, 233467 – C250 – Revision C, 233467 – C251 – Revision C and 233467 – C252
– Revision C prepared by COVEY dated 14 March 2025. The works must include but not be
limited to:
a. construction of kerb and channelling and underground stormwater drainage;
b. widening and sealing of the existing road pavement;
c. line marking;
d. construction of a pedestrian footpaths;
e. removal of the existing redundant infrastructure and reinstatement of the kerb, footpath
and verge area to match the balance of the site frontage, including the provision of
topsoil and turf where the existing verge is grassed;
f. truncation of the existing property boundary at the intersection of Lake Macdonald
Drive and Dianella Court;
g. installation of street lighting.
Condition 13 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
New Roads
14. The new road shown on the Approved Plans must be constructed in accordance with the
conditions of this Decision Notice and dedicated as road reserve.
15. Formalised access must be provided to Lot 100 as part of any subsequent development of
Lot 100.
16. The works must be undertaken in accordance with an Operational Works approval and must
be generally in accordance with drawings numbered 233467 - C003 – Revision C, 233467 –
C010 – Revision C, 233467 – C240 – Revision C, 233467 – C241 – Revision C, 233467 –
C242 – Revision C and 233467 – C243 – Revision C prepared by COVEY dated 14 March
2025.
Condition 16 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Pedestrian and Bicycle Facilities
17. Pedestrian facilities must be provided for the development. The works must be undertaken
in accordance with an Operational Works approval and must include in particular the
footpaths shown on the approved plans.
Condition 17 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Stormwater Drainage
18. The site must be provided with a stormwater drainage system connecting to a lawful point of
discharge. The works must be undertaken in accordance with an Operational Works approval
and must be generally in accordance with drawing number 233467 – C010 – Revision C.
Condition 18 is imposed pursuant to s145 of the Planning Act 2016 being non-trunk
infrastructure.
Page 57 of 61
Document Set ID: 23690498
Version: 0, Version Date: 01/01/1900
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning RAL25 0004 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 3.2 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.