2.4 Audit Team
The Audit Team comprised the following members:
• Matthew Grierson – Senior Road Safety Auditor (Team Leader), Colliers International Engineering &
Design Pty Ltd
• Nilu Seneviratne – Road Safety Auditor, Colliers International Engineering & Design Pty Ltd
• James Knell – Road Safety Auditor, Colliers International Engineering & Design Pty Ltd
2.5 Site Inspection
A site inspection of the audit area was conducted on Tuesday, 8th July 2025. The inspection was conducted
in the day / night to assess the existing road network conditions. The weather condition during the
inspection was clear and dry during the day and at night. The inspection was carried out both on foot and in
a vehicle.
2.6 Drawings Reviewed
The drawings reviewed as part of the Road Safety Audit are listed below.
Avada Traffic – Traffic Guidance Scheme set of drawings (TGS):
• Plan number CMI-1AP-25040286
o CMI-1AP-25040286.1 – Rev 0
o CMI-1AP-25040286.2 – Rev 0
Site: Serenity Close Noosa Heads – Thematic RSA Report
Reference: 22BRT0122 RP01_2_RSA
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Response to Further Advice - Road Safety Audit Report 22BRT0122 RSA_2_250722.pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.2 MB (small file)
- File type
No other editions are linked here.