Council archive · source document
Minor Change Existing Approval MCU21 0117 02 & OPW21 1099 02 (As Published) · OPW21/0199.02
Bioretention Basins
101. During construction and establishment of the bioretention devices, the supervising RPEQ
must ensure that the device was constructed in accordance with the document Construction
and Establishment Guidelines: Swales, Bioretention Systems and Wetlands (Water by
Design, 2009) and that the forms contained in section 3.15 including the associated
supporting information and data are completed. These forms and certification from the RPEQ
that the device has been constructed in accordance with the Construction and Establishment
Guidelines: Swales, Bioretention Systems and Wetlands (Water by Design, 2009), all
conditions of approval, and the approved engineering drawings must be submitted to Council
prior to commencement of use.
102. Deleted
103. Deleted
FOLLOWING CONSTRUCTION / PRIOR TO THE COMMENCEMENT OF THE USE
Certification
104. Upon completion of the work a certificate must be issued by an RPEQ certifying that the
works have been constructed in accordance with the Operational Works permit. Certification
of the completed works must specifically include RPEQ certification that the completed works
conform with all aspects and assumptions of the hydraulic assessment for the development
generally in accordance with Site-Based Stormwater Management Plan (Reference 23098 -
SBSMP/4 Dated 14/5/2024) prepared by Morgan Consulting Engineers
As Constructed Plans and ADAC XML Files (Council)
105. Prior to acceptance of civil works to become Council assets “On Maintenance”, satisfactory
“As-Constructed” records must be submitted to Council. The bundle of “As Constructed”
information shall include:
a. As-Constructed Engineering Drawings. Data is to be submitted in an electronic drawing
file format (.dwg), with all plans clearly endorsed “As-Constructed”, along with the
accompanying hardcopies (PDFs of the As-Constructed .dwg drawing files), and;
b. ADAC XML Digital File. ADAC File format (ADAC - Asset Design As Constructed)
prepared in accordance with industry standards and recorded in “MGA - UTM56 /
GDA94” projection.
Please Note: Further information and advice relating to the as-constructed drawing
presentation, as-constructed survey capture and associated guidelines for preparation
of a compliant ADAC XML digital file are available on the webpage titled “As-
Constructed Guidelines” and accessible at the Noosa Council Website: Planning &
Development / Development Tools & Guidelines / As-Constructed Guidelines.
c. The “As-Constructed” drawings will require certification by a:
i. Qualified experienced Civil Engineer (RPEQ) confirming design intent and
conformance with applicable standards and specifications, along with the
relevant descriptions of assets, services and structures and;
ii. Licensed Surveyor in regard to the cadastral and locational information, levels
and applicable survey datum.
d. The data must be in accordance with Council’s “Planning Scheme Policy 6 –
Engineering Design Standards”, and fully detail the levels for all engineering works
including but not limited to the drainage network and structures, finished ground and
pavement surface levels.
e. The building envelope data must be submitted in both hardcopy and digital format
(ADAC XML Digital File). ADAC - Asset Design As Constructed, is to be prepared in
accordance with industry standards and recorded in “MGA - UTM56 / GDA94”
projection.
Page 17 of 31
Document Set ID: 24681870
Version: 7, Version Date: 17/04/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Existing Approval MCU21 0117 02 & OPW21 1099 02 (As Published).pdfRelated documentApplication case desk ↗
Minor Change Existing Approval MCU21 0117 02 & OPW21 1099 02 (As Published).pdfRelated documentApplication case desk ↗
About this file
- File size
- 924 KB (small file)
- File type
No other editions are linked here.