Minor Change Existing Approval MCU21 0117 02 & OPW21 1099 02 (As Published) · OPW21/0199.02

of 31

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

               27.    All building materials containing asbestos, including asbestos cement sheeting or roofing and
                      lagging are removed from the building prior to demolition/relocation.
                      Plumbing and Drainage
               28.    It is a requirement of the ‘Standard Plumbing and Drainage Regulation 2019’ that at
                      demolition of a building, the existing sanitary drain upstream from the connection point for a
                      service provider’s sewerage system must be sealed water tight. This work is deemed as
                      notifiable Work and must be carried out by a suitably licenced plumber who must submit an
                      As Constructed plan and Form 4 (Notifiable Works Form) to the QBCC (Queensland Building
                      Construction Commission) within 10 days of completing the work.
               LANDSCAPING
               29.    The development site must be landscaped. The works must be undertaken in accordance
                      with the Noosa Plan PSP 2 – Landscaping and generally in accordance with the approved
                      Landscaping Plans and in particular:
                      a.      A dense 2m minimum landscaped setback to the full length of the site’s frontage to
                              Pearl Street (excluding access, fence and bin enclosure).
                      b.      A dense 2m minimum landscaped setback to the full length of the site’s frontage to Elm
                              Street.
                      c.      A dense 1m minimum landscaped setback to all side boundaries (excluding stormwater
                              infrastructure) except along the proposed driveway which adjoins Lot 1 RP153798
                              where a 0.5m wide landscape setback must be provided.
                      d.      The provision of 3 new street trees in accordance with PSP 2 – Landscaping.
                      e.      All landscape works must be established and maintained in accordance with the
                              approved design for the life of the development, and in a manner that ensures healthy,
                              sustained and vigorous plant growth. All plant material must be allowed to grow to full
                              form and be refurbished when its life expectancy is reached.
               ENGINEERING
                      External Works
               30.    Pearl Street must be upgraded for the length of its frontage to the subject site. The works
                      must include in particular:
                      a.      Construction of kerb and channelling and underground stormwater drainage to the
                              development side only;
                      b.      Widening and sealing of the existing road pavement between the edge of the existing
                              road to the new lip of kerb for the width of the frontage;
                      c.      Construction of a 2.0m wide pedestrian footpath in accordance with the conditions of
                              this Decision Notice;
                      d.      Filling in of the table drain for the length of the frontage and providing an underground
                              stormwater line to accommodate flows from the upstream table drain;
                      e.      Removal of the existing property access to 5 Pearl St and reinstatement of the kerb,
                              footpath and verge area to match the balance of the site frontage and proposed works,
                              including the provision of topsoil and turf where the existing verge is grassed.
                      Site Access and Driveways
               31.    A sealed access driveway must be provided from Pearl Street to all parking and manoeuvring
                      areas of the development. The works must include in particular:
                      a.      A driveway crossover generally in accordance with Councils standard drawing RS-051
                              and approved plan 23098 / SK10 Rev G as prepared by Morgan Consulting Engineers.




                                                                                                         Page 6 of 31
Document Set ID: 24681870
Version: 7, Version Date: 17/04/2026

Used in these records

About this file

File size
924 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval MCU21 0117 02 & OPW21 1099 02 (As Published).pdf · 924 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.