Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
65-67 Elanda Street, Sunshine Beach
Site Based Stormwater Management Plan
_____________________________________________________________________________________________
Currently, no stormwater discharge outlet point for the existing dwelling is observed along
the kerb and channel, it is assumed that the stormwater runoff from the development site is
currently discharged to the ground, and flows to the rear of the site as sheet flow.

No information of acid sulphate soil is obtained for the development site. However, given
the site is on an elevation far higher than 5m AHD, it is deemed that the acid sulphate soil
risk here is minimal.




1.4.3 Proposed Land Use and Stormwater Discharge
The existing house and hardstand areas are to be removed, and four (4) townhouses with
associated driveways are proposed for the development. The site dwelling density is approx.
39 dwelling/Ha (i.e. 4 dwellings/0.1020 Ha).

Considering the site dwelling density is over 20 dwelling/Ha, which falls within urban
residential high-density category in QUDM. Based on this the, the minor storm event is 10%
AEP. The site configuration is further detailed in Table 1.2.

A series of field inlet pits and underground stormwater pipe are proposed to collect the roof
water from the below-ground detention tank. Stormwater runoff from the site is proposed to
be discharged to the proposed soakage trenches located at the rea of the property, as
shown in Appendix E.

Table 1.2 Detailed site configuration

            Roof surface area         Landscape area       Driveway area   Total area (ha)
                  (ha)                     (ha)                (ha)
                 0.0500                   0.0325              0.0195           0.1020




File Name:            WCD-22936 – 65-67 Elanda_SWMP.docx
Revision:             E                                                                      7
Log in to download the original file

Revised Stormwater Mangement Plan.pdf · 9.3 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.