Skip to the record
The gold standard in government transparency.

Original source · versioned page text

Revised Stormwater Mangement Plan

Attached to the e-mail Email 2 of 2 - Outstanding Matters - 67 Elanda Street - MCU21/0190.

of 99

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Original PDF page 8, section 1. The text section number identifies this passage in the reader.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
65-67 Elanda Street, Sunshine Beach
Site Based Stormwater Management Plan
_____________________________________________________________________________________________

2. Lawful Point of Discharge
In accordance with Queensland Urban Drainage Manual (QUDM 2016) section 3.4, a Lawful
Point of Discharge (LPD) must be demonstrated when proposing a development. Section
3.4.1 outlines a two-point test to assess whether a lawful point of discharge exists for a
development that consists of the following:

    (i)       The location of the discharge is under the lawful control of the local government
              or other statutory authority from whom permission to discharge has been
              received. This will include park, drainage or road reserve, stormwater drainage
              easement


    (ii)      In discharging to that location, the discharge will not cause an actionable
              nuisance (i.e. a nuisance for which the current or some future neighbouring
              proprietor may bring an action or claim for damages arising out of the nuisance),
              or environmental or property damage.

Currently, the site discharges stormwater naturally to the east downstream area, the existing
LPOD is to remain in the developed case. The roofwater runoff will be mitigated prior to
discharge from the development site.




File Name:            WCD-22936 – 65-67 Elanda_SWMP.docx
Revision:             E                                                                     8
Log in to download the original file

Revised Stormwater Mangement Plan.pdf · 9.3 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.