PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 16 September 2014
ENGINEERING
Site Access and Driveways
6. A sealed access driveway must be provided from Edward Street for the full
length of the proposed access easement. The works must be undertaken in
accordance with an Operational Works approval and must include in particular:
a. A 3m wide sealed access extending from the end of the current formation
in Edward Street to the property boundary,
b. A 4m wide sealed access for the full length of the proposed access
easement including a 5.5m wide passing bay located between the Edward
Street frontage and the access to Lots 1 and 2,
c. Sealed access driveways to Lots 1 and 2 extending from the edge of the
shared access driveway to the boundary of Lots 1 and 2, and
d. Underground service conduits for all utility services.
Stormwater Drainage
7. The site must be provided with a stormwater drainage system connecting to a
lawful point of discharge. The works must be undertaken in accordance with an
Operational Works approval and must include in particular:
a. An interallotment drainage system extending from the boundary of Lot 1 to
James Street;
b. the use of gravity stormwater drainage.
Electricity and Telecommunication Services
8. Reticulated electricity and telecommunication services must be provided to each
lot in accordance with an approval for Operational Works and the standards and
requirements of the relevant service provider.
9. Unless otherwise stipulated by telecommunications legislation at the time of
construction, the development must be provided with all necessary conduits, pits
and pipes to accommodate the future connection of optic fibre technology
telecommunications.
10. Certification must be submitted to Council from all relevant service providers
which certifies that the development has met the requirements of this Decision
Notice and all applicable legislation at the time of construction.
Easements
11. An easement for drainage purposes must be registered against the title of
proposed Lot 2 in favour of Council over the land area identified as being below
the 1%AEP flood level on the subject site.
12. For the purpose of this permit the 1%AEP flood level means the 1%AEP level as
described in a current Flood Certificate issued by Council.
13. An easement for access and services purposes must be registered against the
title of the Lot 3 SP155477 in favour of proposed Lots 1 and 2. The easement
must be located generally in accordance with the approved plan and have a
minimum width of 10 metres.
14. An easement for interallotment drainage must be registered against the title of
proposed Lot 2 in favour of proposed Lot 1. The easement must extend from the
common boundary of Lots 1 and 2 to the James Street frontage.
Page 95 of 145
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.