Original PDF page 108, section 1. The text section number identifies this passage in the reader.

Noosa Civic
Construction Environmental Management Plan



 Tasks                                 Actions / Monitoring                                                                        Timing    Responsibility
                                       Undertake permanent or temporary vegetative stabilisation, e.g. through utilisation of,     works.
                                       where appropriate: 1. topsoil spreading (and compaction, with temporary sediment
                                       controls); 2. grass turfing; 3. surface mulching (note that surface mulching should not
                                       be applied within waters); 4. seeding; and/or 5. planting; in all disturbed areas, having
                                       regard to the future use.
 Record keeping.                       Maintain records of any monitoring results including details of corrective actions and      Ongoing   Contractor
                                       repairs/maintenance undertaken.
                                       Ensure all records and reports are made available to relevant administering authorities
                                       upon request.
 Corrective actions                    Should there be non-compliance with the stated performance indicators the following         Ongoing   Contractor
                                       corrective actions are to be implemented:
                                            identification of the cause of the non-compliance;
                                            implementation of appropriate mitigation measures as determined by the
                                             Principal in consultation with the Contractor and relevant experts (where
                                             required); and
                                            relevant validation monitoring to confirm that the nominated corrective
                                             actions have been effective.
                                       The Contractor shall implement the corrective action(s) as required within the agreed
                                       timeframe noted on the CAR.




Noosa Civic                                                                   Version 1                                                       November 2014
Appendix B - Construction EMP.docx                                                                                                                 Page 15
Log in to download the original file

MCU14_0106 Appendix E - Engineering Report.pdf · 24.1 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.