Noosa Civic
Construction Environmental Management Plan
Tasks Actions / Monitoring Timing Responsibility
systems for temporary vegetative cover within 10 days after grading.
Maintain erosion and sediment Prepare an erosion and sediment control device maintenance schedule and checklist, Prior to Contractor
control devices to ensure they are in general compliance with the example provided in the ESCP to be read in conjunction construction
effective. with this CEMP.
Undertake inspection of erosion and sediment control devices as scheduled, and report Daily, and
any failures immediately on a CAR form. after every
Remove all material from sediment and erosion control devices following rain. Return rain event
uncontaminated material to a secure stockpile area. greater than
25mm.
Keep stockpiles within designated Ensure stockpiles of erodible material are: Ongoing Contractor
and controlled areas (kept as far
formed on flat ground in heaps of no more than 2m in height;
as practicable away from
watercourses) and prevent the appropriately protected from wind, rain, concentrated surface flow and upslope
spread of stockpile material into stormwater surface flows;
adjacent areas. located at least 2 metres from any retained vegetation or concentrated drainage
line;
located up-slope of an appropriate sediment control system; and
provided with an appropriate protective cover (synthetic or organic) if the materials
are likely to be stockpiled for more than four weeks.
Undertake visual inspection of stockpiles and adjacent areas on a daily basis during Daily during
construction. construction
Avoid unnecessary disturbance of Minimise the removal of riparian, bank and in-stream vegetation wherever possible, in Prior to and Contractor
watercourses, including order to reduce the risk of erosion and assist in maintaining the stability of the beds and during
ephemeral watercourses. banks of waters. construction
Do not allow excavators to enter the bed of the watercourse.
Mark any buffer areas in the field, and limit vehicular entry into the riparian zone and
stream banks through fencing or flagging, and/or signage.
Ensure all machinery used in the activities is stored, refuelled and maintained outside
the high banks of the watercourses at a minimum distance of 40m.
Stabilise exposed areas as soon Undertake, as a minimum, the following stabilisation measures at the site. During Contractor
as practicable during and/or Minimise soil exposure e.g. laying gravel, employing an erosion control blanket or construction
following construction. matting. where
practicable,
Retain and/or maintain downslope vegetation/grass cover as a secondary filtration and following
device for stormwater runoff. completion of
Noosa Civic Version 1 November 2014
Appendix B - Construction EMP.docx Page 14
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.