Geotech 95141.00.R.001
From the archive Stormwater Submission.zip, inside Operational Works Application OPW21/0272 Submission - DA Form 1 - Plans - Geotech Report - 32 Viewland Dr, Noosa Heads. File date in the archive: 2021-03-11 08:38.
Page 5 of 10
• It is considered that the majority of materials won from excavations on site where free of organic
and deleterious material will generally be suitable for reuse as bulk fill provided the moisture content
of the soils on placement approximates the OMC.
• Imported fill material, if required, should be a good quality select fill material of low plasticity and
well graded with a maximum particle size of 75 mm. The use of clayey imported fill material will
increase the estimated ground surface movements due to moisture variation and the site
classification.
• Approved structural fill should be placed in layers not exceeding 0.2 m ‘loose’ thickness, with each
layer compacted to a minimum density index of 75% or a minimum dry density ratio of 98% relative
to Standard compaction. Unbound pavement gravel should be compacted to a minimum dry density
ratio of 100% relative to Standard compaction.
• Field density testing should be carried out to confirm the standard of compaction has been achieved
and the placement moisture content. The frequency of testing should be in accordance with
AS 3798. Level 1 inspection and testing of fill must be undertaken where the fill is to support
buildings or pavements.
The above procedures will require geotechnical inspection and testing services to be employed during
construction by an experienced and competent geotechnical testing authority. It is recommended that
earthworks inspection and testing services that will be required during earthworks construction be
carried out by DP.
6.2 Batter Slopes
Very loose to loose sands have the potential to ‘collapse’ unexpectedly in a trenching situation. All
excavations will need to be battered for stability and prior to personnel entering the excavation.
Temporary excavations less than 1 m depth may remain vertical for short periods of time, provided
moisture conditions are favourable at the time of construction and provided there are no loads, services,
structures or traffic located within close distance to the crest of the excavation. Formwork may be
required to prevent loose material slumping into open excavations.
Temporary unsurcharged batter slopes should be no steeper than 2.5H:1V. Where groundwater
seepage is encountered, batter slopes will need to be considerably flatter.
The above temporary batter slopes are suggested with respect to slope stability only, and do not allow
for lateral stress relaxation which may result in movement of nearby inground services or shallow
footings. If such services are settlement-sensitive, and are located near the crest of the excavation, then
the excavation may have to be positively supported.
Long term slopes may need to be flattened to 3H:1V or less, in order to allow vehicle access for
maintenance of grass. It is recommended that all batters incorporate crest and toe drainage. The batters
should also be covered with topsoil and vegetation to provide long term erosion protection.
Geotechnical Investigation, Proposed Youngcare Facility 95141.00.R.001.docx
32 Viewland Drive, Noosa Heads January 2021
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.