               23.    Unless otherwise agreed in writing by the relevant service provider, any public or third party
                      infrastructure located on the subject site must be placed within an easement registered
                      against the title of the property.
               24.    All easements must be designed in accordance with the planning scheme and granted at no
                      cost to the Grantee. Where the Grantee is Council or a service authority, the easement
                      documentation must be in accordance with the Grantee’s standard easement terms. Draft
                      easement documentation must be submitted to Council for endorsement.
               25.    All works must be kept clear of any existing or proposed easements on the subject land,
                      unless agreed otherwise in writing by the Grantee.
                      Geotechnical Stability
               26.    All works must be carried out in accordance with the recommendations contained in Pacific
                      Geotech’s Geotechnical Report (PG-13872) dated August 2025 and endorsed as part of the
                      building approval.
               27.    A dilapidation survey must be carried out of all adjacent properties, structures and
                      infrastructure prior to the commencement of works and endorsed as part of the building
                      approval.
                      Earthworks and Retaining Walls
               28.    All earthworks and associated retaining structures/batters, both above and below ground,
                      both temporary and permanent, must be contained entirely within the subject site unless
                      written permission form the respective landowner(s) is provided to Council. All earthworks
                      must be undertaken in accordance with the provisions of Australian Standard AS3798:
                      Guidelines on Earthworks for Commercial and Residential Developments.
               29.    Where the development involves excavation or filling over, or adjacent to, drainage, water
                      supply or sewerage infrastructure, all access chamber surface levels must be adjusted to
                      provide a freeboard of 100mm above the finished ground surface level.
               30.    All retaining walls must be designed and constructed in accordance with the planning scheme
                      and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
                      are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
                      safety fence.
                      Acid Sulfate Soils
               31.    All works must be carried out in accordance with an Acid Sulfate Soil and Groundwater
                      Management Plan for the development prepared by a qualified person* and endorsed as part
                      of the building approval.
                      *(Refer to Advisory Note)
                      Damage to Services and Assets
               32.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
               Any repair work which proposes to alter the alignment or level of existing services and assets must
               first be referred to the relevant service authority for approval.




                                                                                                     Page 15 of 20

Document Set ID: 24807636
Version: 2, Version Date: 20/05/2026
Log in to download the original file

Amended Delegated Report - Code - Planning - MCU25 0101 (As Published).pdf · 2.1 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.