20220214 12 Wyandra St SWMP

of 53

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (12.5 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Original PDF page 10, section 1. The text section number identifies this passage in the reader.

 STORMWATER QUALITY
The following sections discuss the stormwater quality considerations for the construction and operational phase of
the development.


     4.1. Construction Phase

          4.1.1 Erosion and Sediment Control Measures
During construction, it is necessary to manage stormwater run-off to avoid potential contamination of downstream
waterways from sediments and other pollutants from the site. A range of best practice sediment and erosion controls
should be implemented on the development to ensure negative impacts to the downstream receiving environment
are mitigated.

As the area being developed is below 2,500m², the development’s construction will be managed using best practice
erosion and sediment control principles in line with the desired outcomes of Appendix 2 of the SPP (DERM, July
2017), which are shown below in Figure 4.1.




                     Figure 4.1 SPP 2017 Construction Phase Stormwater Management Design Objectives

A site-specific erosion and sediment control plan shall be prepared as part of a future submission for Operational
Works approval. Suitable erosion and sediment controls for the site may include:

     1. Sediment fencing along downstream of the work areas within the site to prevent sediment from leaving the
        construction area.




                                                                                                       Page 10 of 15
Project number 20220214
File 20220214 12 Wyandra St SWMP.docx, 2022-09-14 Revision 1
P +61 7 5211 1003                A 75 Noosa Drive, Noosa Heads,Qld 4567   E [email protected]    recorconsulting.com
Log in to download the original file

20220214 12 Wyandra St SWMP.pdf · 12.5 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.