Attached to the e-mail OPW14/0197 - Amended Plans for Approval (Email 1 of 5)..
NOTE:
REFER TO N13078-104 FOR SEDIMENT
AND EROSION NOTES AND LEGEND.
CONSTRUCTION NOTE:
STAGE C CONSTRUCTION SEQUENCE AS FOLLOWS:
1. EARTHWORKS IN STAGES C1-C3 AND EROSION AND SEDIMENT
CONTROL MEASURE IMPLEMENTED. STAGES C4-C6 CLEARING ONLY.
2. STAGES C1-C3 TO BE FULLY STABILISED FOLLOWING COMPLETION OF
CIVIL WORKS AS PER COUNCIL STANDARDS.
3. EARTHWORKS IN STAGE C4-C6 AND EROSION AND SEDIMENT
CONTROL MEASURES IMPLEMENTED.
4. STAGES C4-C6 TO BE FULLY STABILISED FOLLOWING COMPLETION OF
CIVIL WORKS AS PER COUNCIL STANDARDS.
NOTE:
REFER TO N13078-106 FOR
SEDIMENT AND EROSION DETAILS.
Zz
PROVIDE TURFING OR
SECURED GEOFABRIC TO
INVERT AND BATTERS
BASE
WIDTH
TYPICAL DIVERSION DRAIN DETAIL
aj eg
AWN WIDTH OF WEIR - 5.00m
Sv \ MINIMUM PONDING VOLUME = 434m?
KOS
a
SSS TEMPORARY SEDIMENT BASIN 4
2 NA ~ f REFER DETAILS.
oN oS BASE LENGTH - 60.00m
RSIS 7 Se BASE WIDTH - 10.00m
SX Se RL INVERT OF BASIN - 7.30
SSSCT RL TOP OF BATTER - 9.30 (MIN)
N.T.S.
w DRAIN TYPE | BASE WIDTH DEPTH MIN SLOPE
=! DIRTY 1 1.50m 0.25m 2.00%
a! DIRTY 2 1.00m 0.25m 1.00%
' DIRTY 3 2.00m 0.25m 1.00%.
| DIRTY 4 2.00m 0.25m 5.00%
=) CLEAN 1.00m 0.25m 6.00%
n
TEMPORARY SEDIMENT BASIN 3
REFER DETAILS.
BASE LENGTH - 30.00m
BASE WIDTH - 18.00m
RL INVERT OF BASIN - 9.00
RL TOP OF BATTER - 10.50 (MIN)
RL OF SPILLWAY - 10.00
RL WATER PONDING LEVEL - 10.00
RL SEDIMENT STORAGE LEVEL - 9.40
RL OF SPILLWAY - 8.80
RL WATER PONDING LEVEL - 8.80
RL SEDIMENT STORAGE LEVEL - 8.20
WIDTH OF WEIR - 11.00m
MINIMUM PONDING VOLUME = 976m?
PROPOSED DETENTION
BASIN LOCATION TO BE
UTILISED AS A
TEMPORARY SEDIMENT
BASIN. REFER SECTION C
SEDIMENT BASIN NOTES - CONSTRUCTION PHASE:
TEMPORARY 1. DURING CONSTRUCTION PHASE BIO-RETENTION BASIN TO ACT AS
TEMPORARY SEDIMENT ° TEMPORARY SEDIMENT BASIN.
2. STORMWATER OUTLETS TO BE TEMPORARILY BLOCKED OFF
SEDIMENT BASIN 4 UNTIL SEDIMENT BASIN HAS BEEN DECOMMISSIONED.
BASIN 3 CATCHMENT 3. BIO-FILTRATION MEDIA IS NOT TO INSTALLED UNTIL SEDIMENT
CATCHMENT \ (3.08Ha.) BASIN HAS BEEN DECOMMISSIONED.
(1.38Ha.)
TEMPORARY
SEDIMENT BASIN 2
CATCHMENT (0.99Ha.)
\Ac
FILE; NIBO78-105.dug DATE; 16-10-2014 TIME: 141
Pxref's: X-NBBOI8-TIT X-NBO78-BASE X-NIBO78-ESC X-NI3078-CONTOURS X-NBB078-CUT-FILL USR; Curtis Boorman
sa [ous enone eee — TTT a ee mar ~ SATE
vera
pe wen ssa 1 INNOVATION PARKWAY, BIRTINYA QM PROPERTIES \ CCOMEULT AUSTRALIA SEDIMENT AND EROSION CONTROL
BE ata ce seme rn oT cee eae a P07) 5436 7888) Fox (7) 9699 6630 ww EARTHWORKS PHASE
pe DRAWN CHECK] ——————— PROMECT New ‘APPROVED SHAUN PILCHER RPEQ 14593 Brown Corsutng (QLD) Pty Ltd Gu PLAN SHEET 2 OF 3
0 ‘oan 8 MATHEW HILL REQ 178 LAKE DOONELLA NOOSA ‘ a ee Rees Bucs Dd As Ee
HE N13078 A (Pee i STAGE Ci - C6 Smart Consulting 'unineun tenable gt my [rn warn N19078-105 .
Slr FOR & ON BEHALF GF BROWN CONSULTING (QLD) PTY LTD otann Canter MeRours Speer Oiryapers dumtion Cat = Lc 4084
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.