    BUNNINGS WAREHOUSE, NOOSAVILLE
    SURFACE WATER MANAGEMENT PLAN                                            (40:^ cafwncp
I   6.          MAINTENANCE REQUIREMENTS

                6.1         Construction Phase & Sediment Control
                During the construction phase, the potential exists for significant increases in the

I               amount of pollutants, particularly sediment, exported from the site. During this period,
                an Erosion and Sediment Control Plan is required as part of the overall Environmental
                Management Plan prepared for the construction phase. The erosion and sediment
                control plan for the site would be completed in accordance with Soil Erosion and
                Sediment Control, Engineering Guidelines for Queensland Construction Sites
                (Institution of Engineers Australia, 1996).

                The completion of construction activities in accordance with an Erosion and Sediment
                Control Plan developed using the above guidelines will minimise the nature of any
                adverse impacts during the construction phase. It is considered that the appropriate
                time for the preparation of the Erosion and Sediment Control Plan is at the Operational
                works stage. Further, it is expected that the requirement to prepare a plan will be a
                condition of any development approval issued with respect to the site.

                Performance indicators for the construction phase will be set as part of the overall EMP for
                the construction phase and in agreement with Council. Should non-compliance with the
                performance indicators occur, the following corrective actions are to be implemented:

                        •   Identification of the cause of the non-compliance;
                        •   Implementation of appropriate mitigation measures as determined by the
                            Contractor in consultation with the Consultant; and
                        •   Relevant validation monitoring to confirm that the nominated corrective
                            actions have been effective.

                It is envisaged that the detention basin will first be constructed as a sediment basin to treat
                runoff during the construction phase, and the same would apply to the car park landscape
                divides to a lesser extent. At the end of construction, the basin and swales would have any
                accumulated sediment removed and the vegetation installed (and the filter, in the case of
                the bio-retention devices). As there is likely to be a significant pollutant load generated as
                the Warehouse is first opened to the public, it may be necessary to replace the filter media
                at intervals until the vegetation is fully established.

                6.2         Ongoing Maintenance

                The proposed maintenance for the bio-retention systems is drawn from the Melbourne
                Water publication WSUD Engineering Procedures: Stormwater (June 2004, Chapter 6):

                        The most intensive period of maintenance is during the plant establishment
                       period (first two years) when weed removal and replanting may be required It
                       is also the time when large loads of sediments could impact on plant growth
                       particularly in developing catchments with poor building controls.




    Bunnings Warehouse                                 Version 1                               15 December 2006
    J \3501-541WP\SWMPdoc                        Commercial in Confidence                              Page 16

Used in these records

About this file

File size
70.0 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

OPW11_0023 Development Application part 2 of 2 Planning Report and Plans 178 Eumundi Noosa Road Noosaville.pdf · 70.0 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.