I   BUNNINGS WAREHOUSE, NOOSAVILLE
    SURFACE WATER MANAGEMENT PLAN                                               (J) Ca.wno
I   7.          CONCLUSION

                Bunnings Warehouse plan to develop a new retail outlet in Noosaville, on the corner of the
                Noosa-Eumundi Road and Gateway Drive.

                The development of the site for its commercial use will lead to an increase in impervious
                area across the site (although it should be noted that there is a far greater landscaped area
                across the site than is normally the case for such development types). An increased
                amount of runoff will occur during a storm, which will flow at an increased rate. To alleviate
                flooding problems on site or downstream of it, a detention basin has been provided which
                will detain flows and release them in a controlled manner over time for all flows up to and
                including the 100-year event.

                The key data for the detention basin is summarised below:
                Table 14     Detention Basin Parameters: Summary
                         Parameter                     Value
                           Volume                     1500m
                            Depth                     1200mm
                         Freeboard                    300mm
                      Outlet diameter                 525mm
                        Outlet invert                 +300mm
                     Overflow weir width                20m
                     Overflow weir invert            +1150mm

                In order to protect the environmental value of the receiving water body, appropriate
                stormwater treatment measures have been adopted for the site.             Modelling of the
                performance of these measures has indicated that the water quality objectives applicable to
                the site and its watercourse will be met. The proposed treatment measures will reduce the
                total annual load of pollutants entering the creek to meet or exceed standard performance

1               targets.

                Discharges from the site will eventually pass to the Noosa River, and so it is important that
                runoff quality be maintained following development. As the human activity expected for the
                site could lead to pollution (particularly from litter and vehicles), bio-retention devices will be
                employed across the car-parking areas of the site to capture nutrients, hydrocarbons and
                gross pollutants. All runoff originating from storms of up to the three month return period
                will undergo treatment by passing through a sandy-loam filter before passing to the
                detention basin.

                This report sizes the detention basin for the site, and suggests water sensitive urban design
                measures to ensure quality is maintained. Quantity modelling of the performance of the
                detention basin indicates that the proposed runoff rate will match the existing in all events
                of up to the 100-year return period. Quality modelling of the treatment train has indicated
                that the water quality objectives applicable to the site will be met in all cases.




I   Bunnings Warehouse
    J\3501-5d\WP\SWMPdoc
                                                          Version 1
                                                   Commercial in Confidence
                                                                                                   15 December 2006
                                                                                                            Page 18

Used in these records

About this file

File size
70.0 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

OPW11_0023 Development Application part 2 of 2 Planning Report and Plans 178 Eumundi Noosa Road Noosaville.pdf · 70.0 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗